The location ofmajor HDDs below is agreed and a working width of 160m at the locations is agreed and there is no objection to the principle that no alternatives to HDDs at these locations should be assessed.
Major HDDs: Landfall River Deben Kirton Martlesham A12 A14/Railway/River Gipping Millers Wood
It is agreed that trenchless techniques will be used for Sandy Lane and there is no objection to the use of trenchless techniques under Lodge Road.
2.6 The principles that have Agreed NE agree that the No comment Agreed Agreed Agreed