All jointing pits would be constructed in fields adjacent to public roads and would need hedgerows removed where present (6m width). Less than 10km of haul road required in areas of difficult access (Ramsholt Marsh / East of the Deben). Future works to be undertaken to determine whether track matting is possible
HDDs required 0 locations
Option 2: Open trenching 37km6m Up to 9 sites (2 primary and 7 secondary) 37km23m
Area of HDD rig site/exits not contained within working width
85.1ha Cable trench spoil + jointing pit spoil
Reinstatement of 37km of haul road, would require some removal of hedgerows (23m width)
10 locations – would be contained mostly within working width
Rig site - 2500m2 Exit - 750m2
Cable pulling
Total time period of works
Equipment needed
Up to 80 operations
Up to 28 weeks spread across a period of one calendar year
Tracked or wheeled excavator Dumper
Concrete truck (about 4m3 required per base)
Generator and lights
Tractor and trailer for cable drum Winch
Wheeled 20T capacity vehicles for delivery of sand and removal of excess spoil
Hi-ab equipped lorry for delivery of materials
4x4 pickup, covered van, or similar vehicles for construction workers
Vehicle Up to 80 operations
Up to 44 weeks spread across a period of two calendar years
Tracked or wheeled excavator Dumper
Concrete truck (about 4m3 required per base)
Generator and lights
Tractor and trailer for cable drum Winch
Wheeled 20T capacity vehicles for delivery of sand and removal of excess spoil
Hi-ab equipped lorry for delivery of materials
4x4 pickup, covered van, or similar vehicles for construction workers
No CCS sites. Delivery of materials Seven CCS sites would need to be re-