Response / where addressed in the East Anglia ONE Environmental Statement (ES)
adverse impacts on sites of European nature conservation importance.
East Anglia ONE ES in Section 24.6. Impacts of the East Anglia ONE Wind Farm and offshore export cable are assessed within this ES in Volume 2.
Suffolk County Council
February 2012 / Preliminary Environmental Information Report
Suffolk County Council
February 2012 / Preliminary Environmental Information Report
Dormice surveys must include linking hedgerows within the cable route.
All survey locations were provided to Suffolk County Council for comment prior to surveys being undertaken, and included connecting hedgerow habitat.
Lack of badger evidence, especially in the Bramford area, is unexpected.
The proposed methodology for systematic searching for setts is acceptable.
The initial assessment did not include a detailed survey for Badgers, however a detailed Badger survey has subsequently identified Badgers along the Onshore cable route. A report of this Badger survey is contained in confidential Volume 5, Appendix 24.13.
Suffolk County Council
February 2012 / Preliminary Environmental Information Report
Suffolk County Council
February 2012 / Preliminary Environmental Information Report
Norfolk County Council
June 2011 / Scoping
Noted further consultation will take place regarding construction and mitigation techniques in relation to Stag Beetles.
Noted that monitoring is not emphasised; essential to ensure mitigation measures are effective and the risk of harm to wildlife is minimised.
ES will need to consider impacts on ecology including cumulative impacts.
Ipswich Borough Council
Suffolk County Council
Preliminary Environmental Information May 2014
June 2011 / Scoping
June 2011 / Scoping
Request that land based and watercourse ecology are considered.
Need to consider cumulative impacts of the whole East
East Anglia THREE Offshore Windfarm
The assessment follows the IEEM guidelines. It is possible that different consultancies may interpret the guidelines in slightly different ways.
Post construction monitoring is proposed within Chapter 24 of the East Anglia ONE ES and is discussed in Section xx.
Impacts on ecology are discussed in Chapter 24 of the East Anglia ONE ES in Section 24.6, including discussion on cumulative impacts.
Impacts on both are discussed in Chapter 24 of the East Anglia ONE ES in Section 24.6.
Chapter 24 of the East Anglia ONE ES assesses the effects
Appendix 23.3 East Anglia ONE onshore ecology consultation, SoCG and