Project: A2953 Client: East Anglia Offshore Wind Limited Title:
5.4 Proposed Markings
36. The markings for the proposed East Anglia THREE site would be agreed in consultation with THLS once the final turbine layout has been selected and would be in line with IALA Recommendation O-139.
5.5 Superintendence and Management
37. EAOW would ensure that they have a reliable maintenance and response regime in place such that the required 99% availability targets are met. The method of ensuring this availability would be defined within an Aids to Navigation monitoring plan which may include remote sensing, secondary lighting or maintenance regimes.