Figure 19.2 Anticipated 90% Shipping Lanes- Post Construction of the Proposed East Anglia THREE Project (100% Fill)
280. Based on the baseline routeing through the East Anglia THREE site and deviations identified around the site, Anatec’s AIS track simulation program has been used to illustrate what the re-routed traffic would look like post development. The simulated data for the displaced routes has been merged with actual AIS data to show what the future case marine traffic scenario would look like for both the partial fill and 100% fill build scenarios. Ten days of simulated data merged with actual AIS data is presented in Figure 19.3 and Figure 19.4 for each respective build scenario.
Date: Doc:
07.05.2014 A2539 East Anglia THREE Windfarm Appendix 15.1 Page: 125