Tender Date Lighting Consultant Cladding
- November 2005 onwards - Pinniger & Partners - GWN Contracts, FGF,
(procurement by work package) Access & Acoustic Consultant C3 Printing and Plan A
Start on Site Date - Buro Happold Aluminium Flashings
- January 2006 Main Contractor - JWD Rainwater Installations
Contract Duration - Urban Splash Build Roof Finishes
- 3-years - MAC Roofing
Gross Internal Floor Area SELECTED SUBCONTRACTORS Roof Safety Installation
- 16,200m
2
& SUPPLIERS - AES
Form of Contract and/or Procurement Sheet Piling Windows
- JCT Management Contract - Stent Foundations - Janex
Total Cost CFA Piling Glazing to Entrance Lobby
- Approx £20M - May Gurney - Intercity Glazing
Client Concrete Frame Curtain Wall to Bar / Restaurant
- Urban Splash - Adana Construction - OJ Taffinder
Architect Bathroom Pods Automatic Vent Systems
- Alsop Architects: - Offsite Solutions - SE Controls and Dyer Environmental
Will Alsop, Duncan Macaulay, Kitchens Architectural Metalwork
Edward Norman, Caroline Koo, Bonny Yu - Arnold Laver Kitchens - STD Manufacturing
Structural Engineer Internal Partitions Electrical Installation
- Martin Stockley Associates - Mansell Finishes Ltd and Eurotech - Carey Electrical
M&E Consultant Joinery Mechanical Installation
- Quartzelec and Fulcrum - P&L Joinery - Townley Hughes
Quantity Surveyor Painting Lifts
- Simon Fenton Partnership - Craigmore Painting - Kone
CDM Co-Ordinator Carpets Car Park Roller Shutter Door
- Rawlings Consultancy Services - PCS Flooring - Stertil Stokvis
Landscape Design Acoustic Flooring, Timber Flooring & Tiles Landscape
- Grant Associates - Quilligotti - Yates Landscapes (UK)
Click here to request literature
Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100