Two iVoltCase Studies


Norland Managed Services and iVolt


help an International Investment Bank reduce their UK carbon output


A global leader in investment management and investment services established a sustainability program in 2007 that measures, monitors and reduces the global electricity energy consumption and associated greenhouse gas emissions in their estate.


Norland Managed Services, part of CBRE Group are recognised as one of the leading facilities, energy and project management providers in the UK. Norland manage the UK BNY Mellon sites and were tasked with reducing the electricity consumption. As a preferred supplier iVolt were asked by Norland to look at one of the Bank ’s sites to see what savings could be achieved following an initiative from Norland’s Energy Manager.


FACTS AT A GLANCE PROJECT/ CUSTOMER DATE OF INSTALL


After a detailed site survey by iVolt engineers an 800A/528 kVa unit was proposed to power the whole site and reduce the voltage from an average of 241v to 220v. The unit was installed in November 2013 under the supervision of Norlands team and the Bank were immediately able to see the benefits through the patented IRT monitor which measures and records savings performance of the unit in real time.


The Bank were so impressed with an immediate saving of approx. £2000 per month that they commissioned Norland to upgrade the unit with iVolt’s GPRS modem so that the savings data can be seen by anyone through the secure web based portal


Investment Bank Norland Managed Services November 2013


ANNUAL KWH CONSUMPTION 1,885,930 IVolt UNIT SIZE ENERGY SAVING


IVO3x800-12-2 7.38% (latest data) CO2 EMISSIONS REDUCTION 63.01 metric tonnes Page 66 20/20 - Our Environment designed by iVolt.


"The overall installation of the iVolt Voltage Optimisation system was completed seamlessly during our clients annual shutdown. I found iVolt to provide a service which was both efficient and professional. Our client is extremely satisfied with the energy savings achieved which exceeded everyone’s expectations”


(David Harkman, Norland Managed Services, Contract Manager).


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116