This page contains a Flash digital edition of a book.
ASSETS, INFRASTRUCTURE & INNOVATION


A study carried out at the beginning of the programme found a likely reduction of 3-4% in overall delay minutes as a result of radio failure. But that didn’t capture the secondary performance benefits, which Network Rail says are substantial, but very hard to quantify.


The infrastructure


Underlying GSM-R is FTN, “the glue that holds everything together” as Network Rail puts it. 15,015km of fibre-cable is installed, and virtually all the physical infrastructure is in place, though not all of it is live yet – some is coming online at the same time as GSM-R commissioning in that area (see panel).


It replaces services that previously had to be bought-in, following the long and winding history of British railway telecommunications infrastructure since the sell-off of British Rail Telecommunications to Racal in the mid- 1990s, which through a series of sales and mergers became Thales Telecommunications Services, while Global Crossing (bought up by Level 3 Communications in 2011) owned other parts of the infrastructure.


Palmer said that relying on external third parties was a vulnerability, as Network Rail lacked control of its own destiny.


The other important infrastructure requirement was installing the thousands of radio masts, which required


a huge consultation and


stakeholder management process, although most of them could be built under Permitted Development Rights. Even so, Network Rail undertook to ensure residents, councillors, MPs and bodies like Natural England and English Heritage were aware of what was being done.


Once the infrastructure was installed and following tests in Strathclyde and with the Cambrian ETCS trial, GSM-R could then start going live on the main network.


The roll-out of GSM-R


As of March 2013, 7,231km were operational, meaning the project was 48% completed. The coming go-lives are as follows:


End of June 2013 – 7,494km operational (roll-out 50% complete). Cardiff Re-Signalling Phase 2. Start of July 2013 – 8,789km (58%). ECML and WCML complete. End of July – 9,510km (63%). North west England and south west Scotland. End of September – 10,609km (70%). Remainder of Wales. End of October – 12,657km (84%). Remainder of Scotland and East Midlands. Mid-December – 13,548km (90%). Remainder


of Midlands.


Start of 2014 – 13,666km (91%). Merseyrail. End of January 2014 – 15,108km (100%). Filling in the gaps in northern England.


NRN will be switched off in the north by the end of 2015, and although there is no formal deadline to turn CSR off, Network Rail said it was hoping to do so by the end of this year.


Some TOCs have more to do than others in preparation for using the new system – Southeastern and Merseyrail, for example.


But overall, Palmer said, the benefits are so substantial that the TOCs “are all looking at having it at the earliest possible opportunity”.


Network change and working with the TOCs


Project manager Gary Porter noted that this was much more than a Network Rail project – it had to involve the ORR, DfT, RSSB, ATOC, all the TOCs and the FOCs. “A lot of what has to be done has to be done by our customers,” he said.


Dave Palmer explained that the introduction of GSM-R was a huge challenge because of this, and because of the rules around network change under the Network Code, with the process of formally notifying TOCs, getting their comments and potentially sorting compensation and other arrangements.


He said: “We were placed in a very complex


FTN/GSM-R infrastructure, kit and training progress


• 15,015km fibre cable installed (99%) • 3,233 FTN/GSM-R sites built (94%) • 2,120 FTN/GSM-R sites commissioned (60%) • 5,326 kits installed (69%) • 3,102 cab radios installed (40%) • 7,965 drivers trained (52%) • 2,377 signallers trained (46%) • 2,007 maintainers trained (42%)


Still to come


• Cab installations to go – 2,439 • Radios to install – 4,663 • Drivers to train – 7,232 • Maintainers to train – 2,814 • Signallers to train – 2,809 • Legacy radio removal – 3,949


situation, with a national change of network from one radio system to another, affecting every individual operator and their vehicles, meaning all of their drivers needed to be trained, their maintainers needed to be trained, etc.


“You can’t swallow an elephant in one bite. Trying to get a national agreement with every operator signed off on it before we started on this proved to be not just a virtual impossibility but a real impossibility.


“So two years ago, we had a huge challenge. We were wondering how we would get through this, as was the rest of industry. So we had to reconsider what the implications and requirements of the Network Code actually were.


“It forced us to work very closely and collaboratively with the operators – that was the only way to solve this particular problem, as otherwise we were looking at stalemate, a situation where commercially, Network Rail and the train operators could not converge. Train operators were not going to commit themselves to something until they were certain of every last detail.


“We created a staged process, outside the requirements of the Network Code, and train operators and ourselves worked together to work up this process. It split the country up geographically and in operator layers over that geography, such that we could reach agreements with individual operators in a manner that didn’t compromise the protections that the Network Code offered other operators.


“We took that proposal, jointly with the operators, to the ORR, and got their agreement, in the middle of 2011.


“We got this process working, even though it was technically outside the Network Code.


“The real success story is that not only did we get it to work, and it’s supported every operational introduction of GSM-R since that date, but also that it’s also being talked about as the way of doing programmes with this level of complexity and that are all-embracing in terms of operators in the future, such as ERTMS.”


www.networkrail.co.uk/aspx/6386.aspx FOR MORE INFORMATION


rail technology magazine Apr/May 13 | 211


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188  |  Page 189  |  Page 190  |  Page 191  |  Page 192  |  Page 193  |  Page 194  |  Page 195  |  Page 196  |  Page 197  |  Page 198  |  Page 199  |  Page 200  |  Page 201  |  Page 202  |  Page 203  |  Page 204  |  Page 205  |  Page 206  |  Page 207  |  Page 208  |  Page 209  |  Page 210  |  Page 211  |  Page 212  |  Page 213  |  Page 214  |  Page 215  |  Page 216  |  Page 217  |  Page 218  |  Page 219  |  Page 220  |  Page 221  |  Page 222  |  Page 223  |  Page 224  |  Page 225  |  Page 226  |  Page 227  |  Page 228  |  Page 229  |  Page 230  |  Page 231  |  Page 232  |  Page 233  |  Page 234  |  Page 235  |  Page 236  |  Page 237  |  Page 238  |  Page 239  |  Page 240  |  Page 241  |  Page 242  |  Page 243  |  Page 244