MET MASTS
FEATURE SPONSOR
MINIMISING MET MAST COSTS Met Masts for offshore windfarms are difficult to install in a short timeframe
Also, their cost can be prohibitive for windfarm developers who are typically unfunded at this early stage of setting up a windfarm. Availability of installation vessels and off-the- shelf products are two of the major obstacles facing developers.
The current interest in floating lidar systems belies the issues they face. Their vulnerability to damage from passing vessels due to their low profile close to the sea means a potential loss of the buoy and expensive lidar system and a critical break in the wind data collection campaign. Also, the collected wind data requires compensation to correct it for the motion.
LOW COST NON-FLOATING SOLUTION Ocean Energy and Resource have developed a low cost non-floating solution that provides a low cost, simple and secure installation in up to 50m water depth. To minimise cost they have eliminated the need for large offshore crane vessels and instead make use of smaller tugs and the simple use of buoyancy to help the installation. This also means the met mast design must be adapted to make it buoyant so it can be towed to site by an ocean-going tug. So how can a
steel tube and mast become a floating vessel?
The innovative registered design, Sea Met (RD), meets all these requirements. A floating gravity base with a horizontal sealed steel tower containing a telescopic mast or, if preferred, a larger working platform for the Lidar also rotated for transport, is towed to site using a tug.
INSTALLATION
Once on site, the gravity base is ballasted onto the seabed using seawater and the tower is rotated using buoyancy aids to almost
vertical. Then the tethers are tightened to completely raise the tower to vertical and the working platform is rotated to horizontal.
If a mast is installed, this is raised section by section and the anemometers and other measurement equipment fitted as it is raised. For a Lidar based system, the Lidar is simply lifted onto the working platform and powered up. A reference mast can be installed easily.
Ocean Energy and Resource Ltd
Evolution of 3.5 MW - Platform Upgrade to the next generation
With its new upgrade the machine will perform at a higher capacity and supply a higher yield.
www.eno-energy.com
74
www.windenergynetwork.co.uk
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83