This page contains a Flash digital edition of a book.
SPONSORS OF DISTRIBUTED WIND


DISTRIBUTED WIND


Our readership may not have heard the expression ‘Distributed wind’. Julian Martin CEO, ICE Renewables (sponsors of this feature) explains...


“Many of our customers in the agricultural and commercial sectors have high local energy demand whether to operate machinery or refrigeration equipment. Distributed wind energy production allows for energy to be produced at the point of consumption and allows the producer to directly offset local energy requirements and feed the excess produced back into the network to be consumed locally. This model is more efficient than centralised energy production as there is less energy loss across the grid.”


ONE YEAR UNTIL DIGRESSION HITTING THE FEED-IN TARIFF MILESTONES FOR MEDIUM WIND


With only one year to go until the Feed-In Tariff (FIT) for wind is due to reduce, ICE Renewables highlights some key milestones to ensure your wind projects stays on track to beat the 2014 April reduction.


KEY DATES December 2013


There are two key dates to remember. If by the end of December 2013 you have planning consent, a valid grid connection offer and you have registered your pre-accreditation for the FIT, you will then be given a further 12 months to get your project installed from the date of pre accreditation.


March 2014


If this target can’t be met, then wind projects will have to be completed and the turbine commissioned by the end of March 2014. time is tight, the difference in the FIT rate reduction could be the difference between a viable and non-viable project, so it is important to understand the steps that need to be taken to beat the FIT deadline.


SPECIFIC DETAIL


Ideally a good site will have been identified with decent wind speed data, a wind study and sound financial backing. To hit the deadline the project should already be underway and ideally in planning or about to be submitted. It can take 6 weeks to get all the technical reports together for a planning submission, longer if further studies are required.


QUALITY OF SUBMISSION The better quality the submission, the better chance of understanding the viability of the project early on and avoiding planning delays. This decision can be complicated further by a lengthy Judicial Review process if you want to appeal.


94


www.windenergynetwork.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116