This page contains a Flash digital edition of a book.
INDUSTRY NEWS


IT’S ALL ABOUT TOFFSHORE DEVELOPMENT


The transport of the 40 nacelles, hubs and (S3) tower sections of the 5 Megawatt (MW) wind energy converters M5000-116 started in September 2012.


The components which weigh several tons (a nacelle has a weight of 233 tons) were contractually shipped to the base harbour for the Trianel wind farm Borkum.


The wind turbines will be stored in Eemshaven until planned installation in spring and the components will be constantly monitored by AREVA Wind.


SUCCESSFUL EXECUTION The transport was successfully executed, thanks to high safety standards for


all participants and the optimised


co-operation with all participating companies.


The 56 metre long rotor blades for the wind energy converters will be transported


for final assembly from Stade to Eemshaven. the trianel wind farm Borkum is an important milestone for the offshore development in the North Sea and important for the offshore wind industry.


STRATEGIC PARTNERSHIPS “AREVA did an excellent job technically as well as logistically” enthused Klaus Horstick, CEo of trianel Windpark borkum GmbH & Co KG.


Jean Huby, CEo of AREVA Wind stated: “The safe and successful transport of the 120 big components of the M5000 wind energy converter was possible thanks to the good co-operation with Trianel. The successful execution is clear evidence for the necessity of strategic partnerships and for the safety spirit within the entire offshore industry.”


RIANEL AND AREVA WIND FINALISED FURTHER PROJECT MILESTONE LOGISTICS


COLLABORATION


Trianel wind farm Borkum is a collaboration of 33 municipal utility companies and the municipal utility company Trianel in Aachen. The wind farm will be constructed around 45 km north of the island of Borkum.


The installation of the tripods and the foundations for AREVA Wind’s wind energy converters, started in June 2012. the 5 MW M5000 is a world-wide first for the exclusively designed wind energy converters for harsh offshore conditions.


AREVA Renewables. www.arevawind.com


YOU! 06 www.windenergynetwork.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116