This page contains a Flash digital edition of a book.
Business profile


Benefit from interchange T


he Whitechapel station project will be delivered in three distinct parts - the refurbishment of the existing


Whitechapel station in the Hammersmith and City and District Line cutting, the construction of a new station bridge concourse above the East London Line cutting and the construction of a new ticket hall behind the retained building fronting on Whitechapel Road. Undertaking this project is BBMV, a


joint venture that encompasses Balfour Beatty, Morgan Sindall and VINCI Construction. The headline works are due to commence midway through this year when the main entrance to the existing station is temporarily moved, allowing work to begin to make way for the new station concourse.


Permanent foundation installation Before this work can commence, Balfour Beatty Ground Engineering (BBGE), Balfour Beatty’s specialist geotechnical division, is busy installing permanent foundations to support the new concourse as well as temporary piling to enable further construction work to be carried out.


These temporary piling works, designed


by BBGE, include piling to support tower cranes for later stages of the construction process and the installation of contiguous pile walls for the East and West stair shaft excavations. Due to the limited access to the site, mini piling rigs have had to be used in place of standard rigs. The two Klemm 702 rigs being used stand just three and a half metres tall and can install piles to depths in excess of 20 metres. In addition to their diminutive height, the rigs can install close up to adjacent structures. For the temporary works they have been installing 86 No 300 millimetre diameter piles up to a depth of ten metres for the contiguous wall that will be excavated to create the East stair shaft, and 12 No 450 mm diameter piles to a depth of 24.5 metres to support the tower cranes that will be used during the main construction phase. A specific challenge at Whitechapel


was the proliferation of obstructions. BBGE says an obstruction is ‘something that materially affects the progress of pile boring operations that could not have reasonably been foreseen at the tender stage or from the contract documentation’. At Whitechapel this includes old track


Page 186 April 2013


Whitechapel station is one of nine new stations being built as part of the Crossrail project and will become an important interchange, lying as it does at the eastern end of the central section of the Crossrail route


and both live and dead utilities services. Ranging between one and two metres in depth, the concrete track required coring before the piles could be installed. Rather than using a ground worker to undertake this work, savings could be made to the programme by utilising the mini piling rigs to core the obstructions prior to piling.


Coring is undertaken by fitting a cutting shoe to the bottom of a steel casing, which is then drilled down through the obstruction to create a pathway for a pile. A typical obstruction on this project


would take between four and five hours to core, making the process slow and painstaking.


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188  |  Page 189  |  Page 190  |  Page 191  |  Page 192  |  Page 193  |  Page 194  |  Page 195  |  Page 196  |  Page 197  |  Page 198  |  Page 199  |  Page 200  |  Page 201  |  Page 202  |  Page 203  |  Page 204