This page contains a Flash digital edition of a book.
SPONSORS OF REGIONAL FOCUS


ABLE SEATON PORT Ready for offshore wind – with


planning and quays in place.


In the last issue, we covered the exciting Able Humber Port – here we take a look at one of the Able Group’s more established sites that boast’s a wealth of heritage and an exciting offer to a variety of players in the modern offshore wind industry.


Able Seaton Port (ASP) is a 51-hectare (126 acres) facility situated on the North


Bank of the River Tees and has planning consents in place for turbine manufacture, assembly, commissioning and use as an installation base for the offshore wind industry.


HISTORY


The prestigious facility is the former Laings Offshore Fabrication Yard where large steel jackets (24,000 tonnes) and gravity- based structures (BP Ravenspurn) were constructed during the 1970/80’s. More recently it has been used by Able UK for ship recycling (Le Clemenceau) and the decommissioning and maintenance of oil rigs (North West Hutton) and jack up rigs.


UNIQUE


It is a unique facility that boasts one of the largest dry docks in the world measuring 355m by 260m – a precious


A&P ENGINEERING SERVICES


A&P is a leading Engineering Services and Fabrication group working with customers to provide solutions the global marine and energy sectors.


STRATEGIC LOCATIONS


Located across three strategic locations in the UK, Tyne, Tees and Falmouth, they are ideally placed to service the burgeoning offshore wind industry.


FACILITIES AND CAPABILITY A&P has capability and facilities second to none enabling the delivery of marine and fabrication services to the renewable energy sector, particularly offshore wind, with yards in close proximity to the development sites and easy access to the sea.


As a key solution provider they are able to offer integrated services across the offshore wind sector and include:


• vessel development, conversion and construction


• vessel mobilisation and demobilisation works


• vessel repairs and refits • fabrication of major balance of plant items e.g. substation platform topsides and jackets


• mass production of multiple foundation structure builds for Round 3


• concrete pontoon systems for offshore wind support vessels


EXPERIENCE


Their track record within offshore wind has been growing rapidly in recent years with major conversion work completed on the Ocean Discovery and European Supporter, two vessels specifically configured for seabed survey and cable laying respectively, through to significant mobilisation works on the Seajacks


A&P Tyne Limited www.ap-group.co.uk


asset that was recently acknowledged by UK Government in the previous round of successful RGF bids - and could be useful for future operations such as the manufacture and deployment of GBS foundations.


IN READINESS FOR OFFSHORE WIND For the offshore wind sector this site is one of the most ‘planning and operationally ready’ locations on the East Coast of the UK. Heavy duty quays 306m long designed to provide depths up to -15m CD are in place. Furthermore, quays surrounding the dry dock (depth of -12m) can provide circa 791m quay length if required.


A ‘RARE GEM’ This facility is indeed a ‘rare gem’ that has exciting times ahead of it. The blend of characteristics at Seaton Port along with the unique approach to the offshore wind sector displayed by Able UK Ltd offers future investors a very strong proposition.


Able UK Ltd www.ableuk.com


Leviathan and Kraken, including the fabrication and installation of two 100T blade racks.


ENERGI COAST INVOLVEMENT As recognition of the huge potential that offshore wind offers industry A&P have been instrumental in bringing together 20 leading companies in the North East of England to actively promote the North East as a single integrated supply chain for offshore wind. With the recent launch of Energi Coast this integrated supply chain can therefore support the full range of offshore wind construction, installation, operations and maintenance solutions required in this complex and challenging sector.


58


www.windenergynetwork.co.uk


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148