This page contains a Flash digital edition of a book.
STATION MODERNISATION AND EQUIPMENT


The upgrading of Balham station has forced contractors to work in a confined area and plan carefully. Pieter Wilke, Southern’s senior project manager, explains how the works are progressing.


C


ontractors working on a £1m project to upgrade Balham station


in south London have had to set up their construction site within the area they are refurbishing, as there is absolutely no ‘spare’ land on which to base themselves.


The works, which began on schedule in early April, have been split up into four phases, and necessitate the building of a new entrance to allow the existing booking hall area to be rebuilt.


Pieter Wilke, Southern’s senior project manager, updated RTM on the progress of the works.


He said: “Work started on schedule and we’re on site and currently working on Phase 1 – the new, secondary entrance.


“There will be massive advantages to passengers. Balham is an important interchange station, especially because of its links with the Underground, and we are seeing a continuous growth in footfall. It means the current layout, with a very tight booking hall area, with a gateline on top of the ticket office, on top of the entrance, on top of the link with the Underground, just doesn’t allow for passenger flow.


“The secondary entrance will provide an alternative for Southern passengers, with another area where they can enter and exit from. Currently it’s Station Road only, in and out, but you will now be able to use Balham High Street as well, which will be fully gated. When the secondary entrance is operational, that will then allow us to refurbish the booking hall area, then make the station more accessible, and lastly to undertake some platform updates and minor refurbishments to tidy up the station as a whole, rather than leaving a patchwork of improved and unimproved areas.”


A temporary ticket office and relocated gatelines will allow contractors to completely overhaul the booking hall and ticket office, which is “really very antiquated”, Wilke said, and struggling to cope with passenger numbers – footfall was around 2.55 million in 2009/10.


He added: “It is uncomfortable to use for both passengers and staff. That’s where accessibility comes into it – we’re installing height adjustable DDA compliant


windows, a level ramp entry from Station Road directly into the station and overall, passenger flow will be vastly improved in the area.”


How much demolition work is having to be done as part of the project?


“There will be some demolition work that will take place in the new entrance area, and involves breaking up the existing floor surface at the rear and in the subway, then also providing major structural support for the proposed canopy to protect the new gateline and the new ticket vending machines.


“Further demolition works also take place in the booking hall, creating an additional entrance with a level access ramp, opening up the hall area, replacing steel screens with new toughened windows and relocating the existing gateline – improving passenger circulation. There will also be a complete resurfacing, with a concrete base and tarmac on top to take the main structure that will go under the canopy. We’ll also be installing cycle shelters at the back.”


The works are part of the National Stations Improvement Programme (NSIP), the DfT-funded programme initially designed to enhance around 150 medium-sized stations across England and Wales.


TIMELINE


Phase 1: New secondary entrance – by June 26


Constructing a secondary entrance, new gateline, ticket vending machine and cy- cle shelters.


Phase 2: Underpass & Ramp – by August 16


Relocation of existing gateline and ramp works, temporary ticket office set up.


Phase 3: Ticket Hall Works – by end of September


Refurbishment of booking hall area.


Phase 4: Platform stairwell and plat- forms – by end of October Stairwell/platforms; deep clean includ- ing painting and decorating, overall completion.


Southern and Network Rail’s contractors on the Balham station works are AECOM for project management, with Osborne Rail as the principal contractor.


Wilke said: “Balham is a very British station - there are unique challenges in terms of retaining operations while not disrupting the connection with the Underground and the passengers currently using the station.


“The site does not lend itself to a construction site set-up. You can picture what the contractor is going through, working within a very limited area, bounded by a main road. We don’t necessarily have extra land or excess Network Rail land to use: everything is currently station, so the construction site set-up is within the area of refurbishment. The contractor had to come up with a unique plan to manage that. The bulk of their stuff was off-site so they have had to tightly manage the scheduling of the receiving and removing of materials.”


Will the improvements allow Balham to cope with continuous growth in passenger numbers?


Wilke explained: “The project, first of all, was to address a station that seriously needed refurbishment and in the process to address passenger flows, which has health and safety implications in terms of getting a large number of people through during peak periods. It’s also been done with growth in mind; Southern has got, as part of our franchise, a commitment to grow our stations. One of the areas we want to grow is the leisure market, so what we’re doing at the station at the moment will help us soak up those numbers as we grow.


“By the end of October we will have a completely refurbished Balham station, with two entrances. At that point though, the secondary entrance is seen to be a peak-hours facility, so initially it will only be open until about 10am in the morning, and from about 4-8pm in the evening.


“That’s the current operational plan. But it’s set up for the future, so depending on the growth in passenger numbers, that could become a full-time entrance.”


FOR MORE INFORMATION Visit www.southernrailway.com


rail technology magazine Apr/May 11 | 69


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188  |  Page 189  |  Page 190  |  Page 191  |  Page 192  |  Page 193  |  Page 194  |  Page 195  |  Page 196  |  Page 197  |  Page 198  |  Page 199  |  Page 200  |  Page 201  |  Page 202  |  Page 203  |  Page 204  |  Page 205  |  Page 206  |  Page 207  |  Page 208  |  Page 209  |  Page 210  |  Page 211  |  Page 212  |  Page 213  |  Page 214  |  Page 215  |  Page 216  |  Page 217  |  Page 218  |  Page 219  |  Page 220  |  Page 221  |  Page 222  |  Page 223  |  Page 224  |  Page 225  |  Page 226  |  Page 227  |  Page 228