This page contains a Flash digital edition of a book.
179. Once at the operational phase, there would be very little evidence of the landfall location or onshore cable route as the majority of the components for each would be buried underground, apart from intermittent kiosks, located discreetly at the jointing pits. The impacts of the landfall location and onshore cable route on all landscape and visual receptors during the operational phase would be not significant.


180. As it is likely that the components of the landfall location and onshore cable route would be left in-situ following decommissioning, then the impacts of this phase will also be not significant.


181. There will be no cumulative impacts in relation to the landfall location and onshore cable route.


29.11.2 182.


Scenario 2: Landfall Location and Onshore Cable Route Impacts


In scenario 2, East Anglia THREE project is added to the current baseline situation, in which East Anglia ONE project has not been constructed. Under this scenario, open trenching would be undertaken along the entire onshore cable route for up to four cables and up to four ducts. In addition to this there would be the requirement for HDD operation at eight locations (including the landfall) and jointing pits and kiosks would be required at up to 48 locations. Access would be via haul road along the entire length of the route. Where the onshore cable route crosses hedgerows, this would be at a maximum width of 35m.


183. Embedded mitigation has been used to reduce the potential impacts by using HDD construction through areas where there are technical or environmental constraints or where the landscape is of a special sensitivity. This means sections would remain undisturbed. The routeing of the onshore cable route has taken into consideration the more sensitive woodlands and hedgerows and attempted to avoid these where at all possible, instead routeing through sections where often the condition of the hedgerows is not as good or where gapping already exists.


184. The most notable impacts relating to the landfall location and onshore cable route would occur during the construction phase. The impacts on the majority of the landscape and visual receptors would be not significant as a result of the construction phase. This finding relates largely to a combination of the localised extents of the construction works, occupying a concentrated area in respect of the wider extents of the receptors; the short-term duration of the construction works; and the reversibility of the impacts through embedded mitigation.


185. Significant impacts would arise relating either to the presence and activity of machinery associated with the Construction Consolidation Sites and HDD


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm Appendix 0 Example


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186