This page contains a Flash digital edition of a book.
SIGNALLING & TELECOMS


GNGE completes phase four of five W


Neil Lindley, delivery director for the GNGE project, gives RTM an update on the phase four works.


ork on the Great Northern Great Eastern (GNGE) Joint Line upgrade has passed


another major milestone, with 15 miles of signalling and 15 modernised level crossings brought into service during phase four of the project this summer.


During the commissioning period, 25 July to 11 August, Network Rail engineers worked round- the-clock to deliver the work from Sleaford North Junction to Gosberton.


Throughout the 16-day temporary closure of the railway, 1930s mechanical technology was replaced with modern electronic systems now controlled from Network Rail’s Lincoln Signalling Control Centre (SCC).


Network Rail’s GNGE Alliance partners have been delivering the works along the route of the £280m scheme: Siemens has been delivering the signalling works, Babcock the track works, and Carillion the civils elements.


These will collectively allow the GNGE Joint Line to become the primary route for daytime freight traffic and permit parallel growth in


passenger services on the core ECML route.


In view of the size of the scheme, and its geographic and operational coverage, the programme has been split into five phases. Phases one and three of the work, between Sleaford and Gainsborough, were completed earlier in 2014.


A multi-disciplinary renewal


Speaking about the recently completed fourth phase, Neil Lindley, delivery director for the GNGE project, told RTM: “We have delivered a multi-disciplinary renewal, approximately 15 miles worth of infrastructure, which includes signalling, telecoms, level crossings and track works across that section delivered by a range of our Alliance partners and sub-contractors.”


He added that during the latest works, the fact that the team delivered 15 upgraded level crossings was quite an achievement. “Annually, Network Rail LNE would only commission around 20. So in this phase, we’ve done three- quarters of what usually would be done in a year,” said Lindley.


The level crossings modernised in phase four


• Blotoft (Old Forty Foot Drain, Helpringham/Donington) – MCB OD • Maltings Lane (Ing Drove, Donington) – Automatic half-barrier • Golden High Hedges (Bull’s Bank/Cowdale Drove, Donington) – MCB OD • Church Lane (Church End Drove, Quadring) – MCB OD • Quadring (Town Drove, Quadring) – Automatic half-barrier • Brewery Lane (North Gate, Gosberton) – MCB OD • Gosberton (B1397 – Station Road, Gosberton) – MCB OD • Cheal Road (Cheal Road, Gosberton Risegate) – MCB OD • Water Drove (Gubbole’s Drove, Surfleet) – MCB OD • Burtey Fen (Burtey Fen Lane, Pinchbeck) – MCB OD • Flax Mill (Langhole Drove, Pinchbeck) – MCB OD • Cherry Holt (Mill Green Road/Cherry Holt Lane, Pinchbeck) – Automatic half-barrier • Blue Gowt (Blue Gowt Lane, Pinchbeck) – MCB OD • Mill Green (Woolram Wygate, Spalding) – MCB CCTV • Park Road (Park Road, Spalding) – MCB CCTV


92 | rail technology magazine Aug/Sep 14


Achieving all this in a single commissioning window was quite a challenge, Lindley told us, especially as 10 level crossings were upgraded to MCBOD (manually controlled barrier with obstacle detector) types. “This has been the largest MCBOD commissioning in the UK,” he said. Two of the remaining five level crossings were upgraded to MCB CCTV (manually controlled barrier with CCTV) and three to automatic half-barriers.


“By removing the old Victorian mechanical system, this moves the old methods into the 21st century,” said Lindley. “The benefits it brings are that the new signalling system all ties back centrally to Lincoln SCC, which reduces operational costs significantly on the route. The new signalling system will convert the old manually controlled switches and crossings into power-operated points, and also enables an improved overall journey time across the entire route for train and passenger performance.”


On top of this, Network Rail has installed and commissioned a brand new FTN (Fixed Telecoms Network) communications network across the whole system that supports the new signalling. It is expected that the new, fully- automated signalling systems should reduce barrier down-time at level crossings and help reduce congestion at these locations.


Challenges


As well as carrying out the signalling upgrades, there were challenges to keep the existing railway running while trying to install the new technology that sits alongside the existing equipment and infrastructure.


The Alliance partners also had to upgrade 15 miles of route during the commissioning period. Lindley said: “It has been important to communicate with all the local stakeholders, including parish councils, farming communities


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164