SIGNALLING & TELECOMS


end, turnkey solution. All of these factors contributed to their decision to select us as their network partner.”


Once the contract was signed, Kapsch


CarrierCom architects created a network design that was closely mapped to Nexus’ technical requirements based on detailed information provided during the tender process. “We drew up a compliant design and created a detailed plan for commissioning, installing and testing the new infrastructure,” says Leindecker. “We will deliver all the key project milestones over the next 18 months.”


Delivering the TETRA network


Kapsch will deploy Nexus’ new TETRA infrastructure, including the core digital network, base stations and cab radios (the communications devices used in metro trains), as well as all the terminals required for the control centres. The new communications system will provide full coverage across Nexus’ area of operations, delivering significant performance improvements compared to the previous analogue infrastructure.


Migration risk will be minimised by Kapsch CarrierCom at every stage of the project.


“We will install the new system alongside the old system, with dispatcher terminals operating on both systems for a period of time,” Leindecker said. “The new TETRA system will be thoroughly tested to ensure that there are no issues before the switchover takes place and the old system is decommissioned.”


The solution in focus


The Kapsch CarrierCom solution for Nexus will include a TETRA core network built on geographically redundant equipment to ensure constant network uptime. In addition, 12 energy-efficient TETRA base stations will be installed, with 19 repeaters providing above-ground and in-tunnel coverage. Trains will connect to the TETRA infrastructure via 93 cab radios, with critical components and critical network communications monitored via state-of-the-art network management and dispatching systems.


To make sure Nexus’ communications systems are constantly available, resilience will be built into all layers of the network. “Our network design is based on four transmitters per site on a ‘2+2’ basis – meaning that there are two transmitters with two redundant spares at each site,” said Leindecker. “If a transmitter fails, the system will still operate as normal until staff arrive for their normal shifts, which reduces support costs dramatically. Technically, the system will remain operational even if three


The TETRA standard


TETRA (TErrestrial Trunked RAdio) is a digital trunked mobile radio standard developed to meet the needs of traditional professional mobile radio user organisations. It has a scaleable architecture allowing economic network deployments ranging from single site local area coverage to multiple site wide area national coverage.


Features include: • Wide area fast call set-up ‘all informed net’ group calls • Direct Mode Operation (DMO) allowing ‘back to back’ communications between radio terminals independent of the network • High level voice encryption to meet security needs • An emergency call facility that gets through even if the system is busy • Full duplex voice for PABX and PSTN telephony communications


Source: The European Telecommunications Standards Institute transmitters fail at any particular site.”


The new Kapsch CarrierCom cab radios will be built on a custom design that mirrors the layout of the previous devices. “The fact that the new cab radios will be set up in the same way as the old ones will make it much easier for train drivers to transition to the new system, minimising training requirements and costs,” Leindecker added.


The benefits for Nexus


Nexus is expecting to see vast improvements in the reliability and security of its radio communications compared to the previous analogue system, which dates back to the early 1990s.


Nexus’ rail infrastructure director Raymond Johnstone spoke to RTM earlier this year, saying: “The radio system we have is obsolete. In terms of quality, it still functions reliably, but you’ve always got to keep ahead of the game when it comes to essential kit like radios.”


He noted then that the next upgrade after the radio system will be the design and build phase of the upgrade of Metro’s train control system, PTI (Positive Train Identification), similar to ARS (Automatic Route Setting) as used by Network Rail.


Johnstone said: “Our system is obsolete and cumbersome in terms of being able to change the codes and to use it as flexibly as we’d like, so it’s definitely time for renewal for a whole host of reasons. It does more than ARS; it drives our passenger information systems and our performance management systems, so it’s got a lot of dependencies. We’ve done a feasibility study, and it will physically link into the radio system. We envisage going out to the market around January/February 2015.”


Leindecker explained more about the benefits of the new set-up. “The system will monitor itself for faults and send alerts to control


terminals automatically if there are any issues – helping to maximise service availability.


“In addition, TETRA signals are also more secure and harder to intercept, which will help Nexus prevent eavesdropping and make it harder for hackers to inject false signals into the network.”


The quality of voice communications will also improve dramatically with the digital TETRA network, he said. “TETRA signals are less susceptible to interference from mobile network signals and the audio quality is far superior to analogue systems.


“Both of these factors make voice


communications more secure and easier to understand in noisy environments, which will be a major benefit for Nexus train operators.”


The TETRA network also offers greater capacity than Nexus’ previous system, ensuring that voice communications are clear even on the busiest routes. “With analogue systems, there’s a risk that voice communications could be dropped due to lack of bandwidth,” said Leindecker. “Now, with the new TETRA solution, critical voice communications will always be available.”


As an additional benefit, the new network will be far more efficient, helping Nexus reduce its energy consumption and carbon footprint. “Modern applications and end user terminals consume less power,” said Leindecker.


“The efficiency of the network components will provide ongoing savings for Nexus, while helping to minimise the negative environmental impact of their operations.”


FOR MORE INFORMATION


W: www.nexus.org.uk W: www.kapsch.net/KCC


rail technology magazine Aug/Sep 14 | 89


Wolfgang Leindecker


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164