This page contains a Flash digital edition of a book.
NEWS


West Coast blockade – late hand back causes delays


Network Rail has had to apologise for a late hand back of the West Coast Main Line after the bank holiday weekend’s blockade, which caused delays for passengers.


It said: “We apologise for the delays caused as a result of the late hand back of the line.


“Everything possible was done to complete the work on time, and we will review what happened to determine what lessons can be learnt so future work at Watford can be delivered and completed as planned.”


The works on one of the UK’s most intensively-used sections of rail infrastructure are part of an £81m project to upgrade the railway around Watford, which has long been a problematic area.


The main contractors for the bank holiday works were AmeyColas and Siemens. Three


signalling


gantries, 30 metres wide and weighing 12 tonnes each, were installed over six lines using a 40-tonne


crane.


began to renew S&C new ballast.


Engineers and add


Network Rail spokeswoman Anne- Marie Batson told RTM before the works: “We’re also renewing five sets of points, including a full- depth ballast renewal for each one. AmeyColas will be delivering the trackwork, with Siemens providing the signalling support for the points’ renewals as well as undertaking works as part of their resignalling scheme.”


Apart from the late hand back, the works


were completed successfully, she said.


As part of the main project, all signalling between Kings Langley and Bushey will be renewed and more than 15km of new track will be laid. The OLE will be made more reliable and Orphanage Road Bridge will be replaced to allow for future line speeds of 125mph.


Network Rail is also replacing three critical junctions north and south of Watford and renewing the signalling system in the area. It will also replace the track crossovers with track that is easier to maintain, reducing future disruption.


Dyan Crowther, route MD for Network Rail, said: “The section of track at Watford is one of the most intensively used, high- speed sections in the UK and has seen


tremendous growth in


traffic and passengers over the last five years. There is never a good time to close the railway but this work is essential to maintain reliable


train services for the


millions of passengers who travel on this route every year.”


The next blockade is the August bank holiday. Network Rail’s bank holiday closures programme causes “less disruption than the only other alternative


of closing the line


for 54 consecutive weekends”, it says.


East West Rail target date slips back to March 2019


on the line have been unveiled. The station,


opening next


summer, will be built on the site of the derelict Water Eaton silo, demolished last year.


Network Rail has nearly finished its Oxford to Bletchley electrification feasibility


study the wider (GRIP 2), East West but


the target date for completion of


Rail


western section has slipped to March 2019. December 2017 had earlier been suggested as the completion date.


Phase 1 of the East West Rail western section, Oxford to Bicester, is still on track for March 2016, and design plans for the new Oxford Parkway station


4 | rail technology magazine Apr/May 14


Rob Brighouse, MD at Chiltern Railways, said: “Oxford Parkway will transform travel between Oxford and London when it launches in summer 2015.”


The upgrade and extension of the Oxford to Bicester line facilitates the new Chiltern Railways service


between Oxford and London, providing an


alternative to the


crowded GWML services via Reading into Paddington.


The western section of East West Rail – Oxford to Milton Keynes and Bedford – is committed and funded. Network Rail and Chiltern Railways are managing delivery of the project via the Bicester to Oxford Collaboration. A joint venture led by Carillion and Buckingham Group is the design- and-build contractor for the £87m works.


The ‘central section’, Bedford-


Cambridge, is at an earlier stage and will be difficult and costly. Campaign group Railfuture


welcomed


the extra


detail


provided by Network Rail in its CP5 Enhancements Delivery Plan but added: “[The 2019 delivery date] is a great disappointment and is the result of the schedule needing three years,


from now to 2017, to


obtain the Transport & Works Act Order to permit the project. And this is for a total of about 30 route miles of re-built line.”


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188  |  Page 189  |  Page 190  |  Page 191  |  Page 192  |  Page 193  |  Page 194  |  Page 195  |  Page 196  |  Page 197  |  Page 198  |  Page 199  |  Page 200  |  Page 201  |  Page 202  |  Page 203  |  Page 204  |  Page 205  |  Page 206  |  Page 207  |  Page 208