This page contains a Flash digital edition of a book.
COLLABORATIVE WORKING


netting have been installed.


be mixed with the existing technology. And, even though the new kit may be temporarily controlled through the Stafford signal boxes, we will shortly migrate everything down to control at Rugby ROC.”


Another key part of the programme will be the installation of bi-directional signalling for all platforms and enabling an increase in the slow line speeds (predominantly used by local passenger/freight services) from 75mph to 100mph between Great Bridgeford (near Norton Bridge) and Stafford. Running from spring 2014 to late 2015 with an August 2015 commissioning date, the majority of the works will also be delivered during weekends and midweek nights.


Norton Bridge flyover


The final phase of the project, which was subject to a Development Consent Order and has been four years in the planning, is the flyover at Norton Bridge that will see six miles of new 100mph railway installed.


Transport secretary Patrick McLoughlin MP finally granted the Order on 31 March 2014 after the application process started back in October 2010. The proposed body of construction work includes a grade-separated junction, 10 new bridge structures and one bridge enhancement, four river diversions, major environmental mitigation works, pipeline, road and footpath diversions and the construction of temporary haul roads.


Main works are scheduled to run from spring 2014 to 2017, with key commissionings in 2016. These works have been preceded by preparatory works carried out under separate planning consent. And, so far, as part of its ecological mitigation works, 14km of great crested newt fencing and 2km of hedge


Matt Clark, project manager of Norton Bridge, said that a key point in the construction phase is between June 2014-August 2015 on the construction of bridge 5 (rail over rail) and 5a (road over rail). “Some of the material we are generating through excavation and cutting means that those bridges need to be in place in order to move key materials for the project,” he stated.


He outlined that construction of the new road junction at Chebsey Lane, to accommodate construction traffic using the main compound, is to be complete by June 2014. And, during the same month, bulk earthworks and structures construction will begin. It is anticipated that track installation on the new alignment will also commence in June 2015.


as developed in Australia – based around one unified agreement where all parties share the benefits and the risks.


Jones said: “We brought the four project partners together and through the Alliance we are hoping to transform the infrastructure delivery of the project, which will be defined through excellence in collaboration and creating a positive lasting legacy for Staffordshire.


“It is not just about going in building and improving the railway; the lasting legacy and how we interact with the community are a fundamental part of what we will be doing. This will not be successful as a programme if we do not do this.”


“By the end of the project,” said Clark, “we will deliver the new flyover, removing a key bottleneck at Norton Bridge junction and segregating intercity, commuter and freight traffic. During Easter 2016 there will be a 102-hour possession period for flyover commissioning, with major works taking place over the May and Spring bank holidays – by doing what we are doing we should save 23 weeks on the original strategy.”


It is also expected that the overall SAIP project, which was originally estimated to cost £940m and is now costing £250m, will be delivered ahead of schedule.


Collaborative working


Of course, another interesting aspect of the delivery is that it is the first major contract to be carried out using the ‘Pure Alliance’ model,


The Alliance manager added that building on the recent completion of line speed improvements between Crewe and Norton Bridge, the last few months have been major milestones for SAIP. “Our key focus now,” he said, “is to deliver these works efficiently and effectively and to minimise the impact they will have on the local community.”


TELL US WHAT YOU THINK opinion@railtechnologymagazine.co.uk


rail technology magazine Apr/May 14 | 33


There have been alliances before to deliver rail infrastructure works, notably the one that delivered the Hitchin Flyover. But they have still basically been an alliance agreement overlaid on top of a more traditional contract. Jones said: “What we are doing here is the next step. It means all four parties need to be aligned; working to certain values and behaviours in a collaborative manner.”


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188  |  Page 189  |  Page 190  |  Page 191  |  Page 192  |  Page 193  |  Page 194  |  Page 195  |  Page 196  |  Page 197  |  Page 198  |  Page 199  |  Page 200  |  Page 201  |  Page 202  |  Page 203  |  Page 204  |  Page 205  |  Page 206  |  Page 207  |  Page 208