This page contains a Flash digital edition of a book.
material selection | DFM


Table 1: Savings resulting from value engineering analysis of a water meter part produced in brass, POM and reinforced PA6,6


Volume/Year Material Volume/part )


35,000 35,000


35,000


Brass POM


PA6,6


(cm3 281 281


208


Density (g/cm3


)


8.4 1.4


1.14


weight/ part (g)


2360.4 393.4


237.12 weight/


35k pcs (t) 82,614.00 13,769.00


8,299.20


PA reinforced with 30% glass fibre it was possible to reduce the overall wall thickness and, due to the new material’s characteristics, reduce the cooling time. The higher raw material price of the glass reinforced polyamide meant there was very little cost saving from the alternative material option. However, the savings in cycle time (-18%) were significant and estimated to amount to about €45,000 a year. The faster cycle time meant it was also possible to


reduce the total tooling requirement. Eliminating the need for an additional four-cavity mould resulted in an estimated additional cost saving of around €68k in this project.


The DFM stage of any product development pro-


gramme is also the appropriate time to carry out some value engineering calculations to determine if the mechanical properties, visual quality and other properties resulting from the incorporation of costly additives such as fire retardants in the material selection are in line with the overall project goals. Recently, AST was involved in just such a value engineering project for a water metering component. The client wanted to replace a part originally cast in brass and capable of withstanding a water pressure up to 12 bars. The main goal of the project was to reduce the component cost while maintaining similar mechani- cal properties, such as dimensional stability and resistance to water absorption.


Figure 2: The thick wall


sections in this POM water


meter compo- nent design required a


cycle time of around 120s. Switching to


reinforced PA presented big


cost reduction opportunities.


50 INJECTION WORLD | October 2012


Price/ kg (€)


3.50 € Design Comment original design 2.50 € 35% material saving


Material Costs (€)


289,149.00 €


1.80 € POM version of original 24,784.20 € optimised design


20,748.00 € Switching from brass to an injection moulded POM


(Figure 2) but retaining a similar wall thickness to the original part not only reduced the material cost significantly, but was also able to meet the high mechanical requirements. However, by introducing a water resistant, glass reinforced PA6,6 into the analysis it was possible to develop a component design with a much thinner overall wall thickness and increased overall strength. Analysis of this thinner component design in PA6,6


showed the cycle time could be reduced from 120s (for the POM part) down to 50s. The overall savings achievable by using the new PA component compared to


the POM version was calculated to amount to around €45,000 a year. The main bulk of this saving was accounted for by the faster cycle time, resulting predominantly from the shorter cooling times required for the thinner wall thickness. The full breakdown of the cost savings for the two


alternative polymer-based components against the the cost for the original brass design are shown in Table 1. It should be noted, however, that the weight savings in the plastic designs also provided a further and quite significant saving on shipping charges. Experience shows that material selection can have a huge influence on part cost and production economics. Companies that take an intelligent approach to resin selection will realise valuable capital and production cost savings, speed their time-to-market, and produce parts that perform better.


About the author: André Eichhorn is general manager of Germany-based AST Technology. This is the second instalment in a series of articles presenting a step-by-step discussion of the Design for Manufacturing (DFM) process. If you missed the first instalment in this series you can view it here. Part three, which will be published in the next edition of Injection World, will look at optimisation of part structure. ❙ www.ast-tech.de


AST Technology will also be exhibiting at the Fakuma trade fair in Friedrichshafen in Germany later this month. You can find the company in Hall A1, Stand 1302.


www.injectionworld.com


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116