PERMANENT WAY SOLUTIONS


£12m N


etwork Rail and ScotRail have agreed a £12m alliance to fast-track the Paisley


Canal line upgrade earlier and bring it in under budget.


The joint investment will be used to electrify the 8km stretch of line between Glasgow Central and Paisley Canal by December 2012. The contract has been awarded to Babcock, recently named Network Rail’s ‘Supplier of the Year’ at the Partnership Awards.


Cost savings for the project will be achieved through the use of extended ‘neutral’ sections when passing under overhead structures, requiring


less rebuilding, and a careful assessment of required clearance heights.


The track will be lowered at key points to


electrifi cation for Paisley Canal line through new alliance


Steve Montgomery, managing director of ScotRail, and Susan Anderson, Network Rail’s route commercial manager, explain how the alliance between the two companies to upgrade the Paisley Canal line is working.


provide suffi cient clearance. This will allow a DMU to operate if no EMU is available and will permit potential future freight traffi c to Hawkhead station.


ScotRail has also waived its right to disruption compensation payments from Network Rail.


Susan Anderson, Network Rail’s route commercial manager, said: “This is the fi rst tangible benefi t for rail customers to be delivered through this alliance with ScotRail. We are delighted to be able to achieve this much more quickly than under traditional arrangements.”


Steve Montgomery, managing director of ScotRail added: “This work is set to deliver substantial benefi ts for customers while driving


down costs. The groundbreaking alliance is a leaner, more effi cient way of working and sets the standard for future rail projects in Scotland.”


Most of the possessions will take place during the evenings, but there will also be some weekend/holiday working to ensure the project can be completed by December.


During the peak, the line will be served by ScotRail’s new Class 380 Desiros EMUs, with older BREL-built Class 314s used during the day.


Transport minister Keith Brown praised the alliance initiative and said: “This is a fi ne example of joining forces to deliver a cost- effective solution that support the Scottish Government’s ambitions for electrifi ed rail across the network. However, the big winners from the investment are passengers who will notice a marked improvement in performance, comfort and seat availability.”


Bob Whiley, managing director at Babcock, added: “We are delighted to be a part of this electrifi cation project, working with Network Rail and ScotRail to help deliver greater effi ciencies for the Scottish rail network.”


The closer working between Network Rail and ScotRail was highlighted by an unprecedented joint apology released in May for poor performance on services between Glasgow and Ayrshire, Renfrewshire and Inverclyde over the preceding year – blaming severe weather, vandalism, and the impact of engineering works associated with the Glasgow-Paisley upgrade itself.


TELL US WHAT YOU THINK opinion@railtechnologymagazine.com 54 | rail technology magazine Aug/Sep 12


© L.Hoon


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156