£100m investment for Nottingham rail network


Kate Ashley reports on the upcoming changes to Nottingham’s rail infrastructure. N


etwork Rail is embarking on a £100m renovation and refurbishment of the tracks, signals and station in Nottingham.


The plan is to re-lay six miles of track, install more than 140 new signals and expand the station, all designed with the Government’s plans to electrify the line to Nottingham in mind, announced in the HLOS (see page 14).


Three signal boxes and two footpath crossings will be closed and two level crossings to the east will be renewed.


Network Rail route managing director Martin Frobisher said: “This investment in Nottingham will bring a huge improvement for passengers. Nottingham is such an important city in the East Midlands and the station improvements will create the gateway which the city deserves. The improvements to the railway infrastructure will improve the fl exibility, speed and reliability of the services to and from the city.”


The plans will be coordinated with other projects that the city is undergoing, most notable the Nottingham Hub Project which includes the expansion of the station to include another platform, a refurbished main entrance hall and a new southern entrance linking to the tram station being built on a bridge over the railway. The wider Hub project is being delivered by Network Rail, Nottingham City Council and East Midlands Trains.


Some work on the resignalling element has already begun, with some gantries now in place, but the bulk of the work will take place next summer.


David Horne, managing director of East Midlands Trains, welcomed the investment and said: “We are pleased that Network Rail will be making this investment in the railway at Nottingham. We will be working closely with them over the next year to prepare for the major work and keep our passengers informed about the changes they can expect to their service in summer 2013 when this important improvement work will be carried out.”


rail technology magazine Aug/Sep 12 | 125


The refurbishment and expansion of Nottingham station is due to start in September and the installation of the new signals has already begun. The signalling has been commissioned for August 24 and 25 next year – marking the end of Trent power signal box after 44 years of service – while the Hub Project is due to be fi nished by December 2013, and Nottingham’s extended tram system is set for completion in late 2014.


The area will come under the control of the latest generation of signal control centres at Derby, delivering greater reliability and effi ciency, Network Rail said.


i More stories like this at:


www.railtechnologymagazine.com/ track-and-signalling


TELL US WHAT YOU THINK opinion@railtechnologymagazine.com


Timetable changes will be in place between July 20 and August 26 next year, with many bus replacement services likely.


Frobisher said: “We realise this will cause disruption to passengers and have made every effort to minimise the length of time our resignalling will take. As the summer is the quietest period for the railway, this is the best time to do the work. We have worked very closely with the cricket ground to make sure that the railway improvement work does not confl ict with the Ashes test match. A full timetabled train service will operate throughout the test match.”


© mattbuck


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156