This page contains a Flash digital edition of a book.
CS6 CS7 CS8


Bullenhall Farm


Walnut Tree Farm


Medium 30


Burstall Hall Medium 27 Medium 26


35 32 31


Negligible Negligible Negligible


Negligible Negligible Negligible


162. The results show that noise levels would be of negligible magnitude on receptors of medium sensitivity and therefore of negligible significance.


Potential Impacts during Decommissioning


163. The decommissioning of the onshore electrical connection, including the cable route and converter station will form part of an overall decommissioning plan. The decommissioning methodology would need to be finalised nearer to the end of the lifetime of the project so as to be in line with current guidance, policy and legislation at that point. Any such methodology would be agreed with the relevant authorities and statutory consultees.


164. It is anticipated that the onshore cables would be decommissioned (de-energised) and the cables and jointing pits left in-situ. In this case there would be no impact for any receptor upon decommissioning. However, where cables are installed in ducts (under Scenario 1) it may be possible to remove and recycle them in which case impacts to receptors would be similar to, but likely be of lower magnitude than those described for construction in section 26.6.1. It is assumed that the jointing pits would be left in-situ.


165. In relation to the converter stations the programme for decommissioning is expected to be similar in duration to the construction phase. The detailed activities and methodology will be determined later within the project lifetime, but are expected to include:


    


Dismantling and removal of electrical equipment; Removal of cabling from site;


Removal of any building services equipment;


Demolition of the buildings and removal of fences; and Landscaping and reinstatement of the site.


166. Noise impacts associated with the decommissioning of both the cable route and converter stations will be similar to those identified for the construction of both elements.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 26 Noise and Vibration Page 43


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58