This page contains a Flash digital edition of a book.
144. It is not deemed that other site or off-site mitigation is required for receptors expected to experience minor impacts, due to the small exceedance of the construction noise ‘limit’ and the relatively short duration of the impact.


145. CCSs will be established close to the landfall, along the cable route and for the converter stations. The CCSs will generally be used for storage of materials, equipment and plant. The selected CCS locations are not in the immediate vicinity of residential properties. As such, it is considered that they will not result in any significant construction noise affecting receptors and will therefore have a negligible effect.


Impact 3: Increased noise on residential receptors during converter station construction 146. Under both Scenario 1 and 2 a new converter station will be constructed feeding into the National Grid at the nearby Bramford national grid substation.


147. The construction of the converter station may involve the use of driven piles to provide suitable foundations for heavy transmission plant and the buildings required to enclose most elements of the converter station.


148. There are no properties within the construction noise impact buffer around the converter station, as outlined in Table 26.7 and shown on Figure 26.4. Therefore on- site construction works associated with the construction of the converter station under either scenario are predicted to result in an effect of negligible magnitude and therefore a negligible impact.


Impact 4: increased noise on residential receptors from off-site construction traffic noise 149. Table 26.24 shows the calculated increase in traffic flow on the road links identified by the transport assessment as carrying construction traffic (see Chapter 27 Traffic and Transport).


Table 26.24


Link ID


1 2 3


Link Description


A14


between the J51 and J52


A14


between the J52 and J53


A1156 south from J53


21,093 447 21,202 519 0.5 21,305 572 1.0 63,085 7,980 63,413 8,250 0.5 63,848 8,605 1.2 Construction traffic impacts


2018 Baseline flows AAWT


Total Vehicles


57,376


Total HGVs


5,973


2018 Baseline + Scenario 1


Total Vehicles


57,573


Total HGVs


6,129


Overall Increase


% 0.3


2018 Baseline + Scenario 2


Total Vehicles


57,839


Total HGVs


6,339


Overall Increase


% 0.8


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 26 Noise and Vibration Page 38


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58