This page contains a Flash digital edition of a book.
133. It is not deemed that other site or off-site mitigation is required for receptors expected to experience minor impacts, due to the small exceedance of the construction noise ‘limit’ and the relatively short duration of the impact.


134. CCSs will be established close to the landfall, along the cable route and for the converter stations. The CCSs will generally be used for storage of materials, equipment and plant. The selected CCS locations are not in the immediate vicinity of residential properties. As such, it is considered that they will not result in any significant construction noise affecting receptors and will therefore have a negligible effect.


Scenario 2: Open Trenching and Laying Ducts


135. Under Scenario 2 a programme of installing four cables and up to four ducts along the cable corridor will be undertaken. In order to facilitate the construction work a temporary haul road will be built along much of the onshore cable route and then removed once works have been completed. In eight locations HDD will be used to install a series of ducts under obstacles, water courses or sensitive areas. A more detailed description of the proposed works is provided in Chapter 5 Description of the Development of this PEIR and the onshore cable route shown in Figure 26.1.


136. A construction noise screening exercise was undertaken using a 65dB LAeq, 12hr impact buffer. An overview of the 65dB LAeq, 12hr construction noise buffer is shown in Figure 26.3.


137. The predicted noise level at each of the selected receptors is presented in Table 26.20.


Table 26.22


Receptor ID


NSR1


NSR2 NSR3


NSR4


NSR5 NSR6


NSR7 Construction noise levels calculated at specific identified receptors Property


Noise from cable installation dB LAeq 12hr


Low Farm 73 Dukes Hill


Cherry Tree Farm


Glebe Farm


The Common


Copenhage n Cottage


Bullenhall Farm


Preliminary Environmental Information May 2014


69 72


71


73 74


65


Noise from major HDD dB LAeq 12hr ----


62 ---- ---- 66 ---- 58


Total Noise dB LAeq,12h 73


70 72


71


74 74


66 East Anglia THREE Offshore Windfarm


Impact magnitude


Medium


Medium Medium


Medium


Medium Medium


Low


Impact Significance


Moderate adverse


Moderate adverse


Moderate adverse


Moderate adverse


Moderate adverse


Moderate adverse


Minor adverse


Chapter 26 Noise and Vibration Page 36


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58