Potential Impacts during Construction Impact 1: Increased noise on residential receptors at landfall Scenario 1: Pre-installed ducts


112. Under Scenario 1 it is assumed that East Anglia ONE project has been constructed. Consequently the ducts required for East Anglia THREE are pre-installed. As a result under the worst case, short HDD installation, the works on site will require access to the beach for tracked plant to enable the landfall trenching of the cable and to assist in pulling the cable through the pre-installed duct to make landfall at the transition pits.


113. There will also be a requirement for temporary works associated with the Onshore Cable Route and converter station enabling works for example the establishment of a haul road and Construction Consolidation Sites (CCSs)


114. As a worst-case scenario, it has been assumed that at the landfall location construction plant equipment will be required during normal daylight working hours for duration of 10 weeks. Table 26.16 presents the predicted noise level at the nearest residential receptor including embedded mitigation, as outlined in Table 26.2.


Table 26.16 Landfall HDD Noise HDD Location


Bawdsey Landfall Ferry Road residences


Nearest receptor to HDD


Approximate Distance to HDD


300 m


Predicted Receptor Noise level


25dB(A)


Impact Magnitude


Negligible


115. The results show that predicted noise levels from construction works at the landfall location would be of negligible magnitude on receptors of medium sensitivity and therefore impacts would be of negligible significance.


Scenario 2: Trenching and installing ducts


116. Under Scenario 2 it is assumed at landfall a HDD compound will be constructed to permit the use of HDD equipment to drill under the shoreline and install ducts into which East Anglia THREE cables can be pulled. In addition suitable ducts for East Anglia FOUR will also be installed as part of East Anglia THREE work. Access to the shore by tracked plant will also be required to assist in cable landing and pulling operations.


117. As a worst-case scenario, HDD has been assumed to be in operation at the landfall location for 24 hours a day for duration of 10 weeks. Table 26.17 presents the


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 26 Noise and Vibration Page 32


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58