predicted noise level at the nearest residential receptor including embedded mitigation, as outlined in Table 26.2.


Table 26.17 Landfall HDD Noise HDD Location


Bawdsey Landfall


Nearest receptor to HDD


Ferry Road residences


Approximate Distance to HDD


300 m


Predicted Receptor Noise level


52dB(A)


Impact Magnitude


Medium


118. The results show that predicted noise levels from the HDD at the landfall location would be of medium magnitude on receptors of medium sensitivity and therefore impacts would be ofmoderate adverse significance.


119. To reduce potential construction noise impacts at the Ferry Road receptors where the impact magnitude is predicted to be medium, a solid site boundary hoarding fence, approximately 2.4m in height, will be erected prior to commencement of landfall operations and remain in place until the works are completed on the landfall.


120. BS5228 states that where a barrier completely screens line-of-sight of a noise source, a reduction of around 10dB can be expected. Any barrier should be of a substantial construction, with no holes or gaps and be approximately 10kg/m2 in density


121. Table 26.18 presents the residual impact of the landfall operations on the Ferry Road residences, providing the mitigation outlined in Section 121 is fully implemented.


Table 26.18 Landfall HDD Noise HDD Location


Bawdsey Landfall


Nearest receptor to HDD


Ferry Road residences


Approximate Distance to HDD


300 m


Predicted Receptor Noise level


42dB(A) Residual Impact Negligible


122. Table 26.18 demonstrates that a negligible residual impact is predicted for the landfall operations near the Ferry Road residences following the deployment of proposed mitigation.


Impact 2: Increased noise on residential receptors during onshore cable works Scenario 1: Pre-installed Ducts


123. Under Scenario 1, as part of East Anglia ONE suitable ducts will have been installed for use by the East Anglia THREE project. As a result the approach to cable installation is comparatively light with respect to the use of noise generating


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 26 Noise and Vibration Page 33


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58