This page contains a Flash digital edition of a book.
Architecture & Art | AUSTRALIA – NEW YORK About the Construction of


KAUST Breakwater Beacon THE STRUCTURAL FORM


The tapered tower is 60m high and divided into three sections, each representing a separate theme. The base is approximately 30m × 25m, reducing to 3m × 2.5m at the top. The first 22m in height is a true shell shape, being anticlastic in form and similar to hyperboloid shapes commonly used in water reservoirs and airport control towers. Beyond that, the spire follows a cone- shaped tapered tower that, at all times, maintains its elliptical form in section. The entire tower is punctuated with hexagonal penetrations that are initially sized up 5m and very irregular in shape at the base, with a transition into a regular size, approximately 0.3m at the apex. There are four doorways as entry points to the internal atrium space, which vary in height up to 12m.


Due to the large number of penetrations and the discontinuities created by the doorways, the structure does not have sufficient continuity to act as a pure structural shell and tends to act like a grillage of continuous beams. The structure was further challenged by the need to split these beams into precast and in- situ concrete components to meet the quality of finishes required.


The lower 22m of the superstructure is comprised of 187 individually-cast hexagonal blocks, each weighing between 2.7 and 18 tons. These blocks were L-shaped in cross-section and, when positioned, formed a U shape with the adjoining hexagonal block. This U was then filled with in-situ concrete to create the structural grillage of beams to support the tower. The outside was covered with precast rings so that only the precast concrete was exposed. The structural sizes for the concrete sections varied from 1m deep × 0.7m wide at the base to 0.55m deep × 0.45m wide at the 22m height.


The framing around the doorways needed to be strengthened due to the concentration of loads and the fact that the doors were a discontinuity in the shell form. These doorways were constructed of structural steel sections fully welded into a continuous frame on-site and then encased in the concrete.


The spire of the tower was made entirely of precast concrete, constructed in complete rings up to 6.9m high or in halves for a similar height. These sections were fully reinforced and then bolted together on-site. The thickness of these sections reduced to 0.18m at the very top.


There was no repetition in the geometry. This presented an extremely complex engineering challenge for Robert Bird Group, which was commissioned to undertake all the engineering for the design, development and construction activities associated with the tower.


About the CONSTRUCTION


The hexagonal elements were constructed using a combination of precast and in-situ poured concrete. First, the internal hexagon was precast off-site in a factory environment and lifted into place on-site using a variety of cranes including one of the largest in the world, a 550-tonne mobile crane. The four teams of surveyors worked on locating the correct positions, within a 20mm tolerance.


Once the internal hexagon was placed, steel reinforcement was then inserted and an in-situ pour completed, stitching each hexagon to its surrounding pieces. When the stitching was completed, the outer skin was then completed by fixing hexagonal biscuits to the outer surface. These slotted into the internal hexagons and concealed the in-situ pour. The dramatic upper spire of the tower is made solely from these precast blocks. The Beacon is located on reclaimed land to form a harbor for the new marina at the university. Construction within the tidal zone required the installation of dams to enable this work to proceed. The footings for the tower consisted of 150 piles, 90 under the Beacon itself and 60 in the outer ring, each with a 750mm-diameter and penetrating an average of 22m deep into the natural dense gravels. These piles and the 2m-deep pile caps were required to support the dead weight of the structure as well as provide a sufficient base for the wind and seismic loads. Additionally, the Beacon is also supported by a 1.5m- thick pile cap ring involving


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136