This page contains a Flash digital edition of a book.
would discharge to local drainage ditches through silt traps, as appropriate, to minimise sediment release.


356. Subsoil would be excavated to the required depth for each trench. This would follow the profile of the ground surface, but deeper excavations could be required at certain crossings.


5.6.4.3 Temporary Roads 357. A temporary haul road, or ‘running track’, would then be installed along the route between access points onto local roads.


358. Temporary haul road construction would most likely involve the placement of a suitable imported material onto a geotextile base and / or use of temporary mats (often referred to as ‘bog mats’).


5.6.4.4 Installation of Cables 359. The onshore power cables and FO cables would be buried in a trench of up to 1.5m depth (except where HDD is required).


360. Cables would be laid in open trenches which are excavated by using a standard mechanical excavator or specific trenching machine. Once trench preparation has taken place, the cables are laid and the trench is back-filled with the original material. It is likely that alternative material would be required to surround the cables if the original material is not deemed to have suitable thermal dissipation and physical characteristics.


361. Cables would be laid on a bed of stabilised backfill to ensure a consistent homogeneous medium for the dissipation of heat generated by the cables. The stabilised back-fill may be covered with cable tiles or other protection and the trench back-filled with the material excavated from the trench. A warning marker tape would be placed at above the cable tiles


362. Site clearing and preparation (establishing vehicle access) would be required prior to the commencement of cable laying. Once the cables have been laid, the land would be returned to its previous condition. Where necessary, reinstatement of internal drainage networks would be necessary for each installation method. Appropriate planning would be required in order to ensure that disturbance to habitat features is avoided or minimised during critical times.


363. As part of the detailed route survey works, soil would be analysed for its thermal properties. If it is suitable (i.e. its thermal resistivity is consistent and in line with the design parameters that have been used to calculate the cable ratings), it can be used


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 79


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114