This page contains a Flash digital edition of a book.
5 DESCRIPTION OF THE DEVELOPMENT


5.1 Introduction 1.


2.


This chapter provides a full description of the components required for construction, operation and decommissioning of the proposed East Anglia THREE project and the methods of installation.


A brief overview of the project is presented in section 5.2 followed by an outline of the key project characteristics in section 5.3. A detailed description of all aspects of the project is provided in sections 5.4 to 5.6 which is divided into the following three areas:


 Offshore - wind turbines, offshore collector stations and converter stations, meteorological masts and their foundations, and offshore export cables, fibre optic cables, interconnection cables and inter-array cables;


 Landfall - work to connect offshore export cables to onshore export cables and provide maintenance access; and


 Onshore - onshore export cables, the onshore converter station(s), and work to construct and access these components.


5.1.1 Project Design Envelope 3.


4.


Section 3.5 of Chapter 3 Policy and Legislative Context provides a background to the design envelope approach.


The project design envelope sets out a series of design options for the project. The project design envelope has a reasoned minimum and maximum extent for a number of key parameters. The final design would lie between the minimum and the maximum extent of the consent sought, for all aspects of the project, this includes spatial, temporal and installation methodology. The project design envelope is used to establish the extent to which the project would impact on the environment. The detailed design of the project could then vary within this ‘envelope’ without rendering the assessment inadequate.


5.


The general principle of the assessment is that for each specialism, the impact assessment is based on a range of project design parameters (e.g. the minimum and maximum tip height of wind turbines that could be used, are between 178 and 247m above lowest astronomical tide (LAT) and the minimum and maximum blade length is between 75 and 108m), the key being that those parameters selected represent the range of options within which the greatest environmental impact would occur.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 1


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114