This page contains a Flash digital edition of a book.
428. A permanent easement would be sought by EATL directly over the cables. The easement would seek to restrict activities which would penetrate the ground by more than 0.5m. As such, it is expected that normal agricultural activities would be able to continue.


429. Routine maintenance is anticipated as consisting of one annual visit to jointing pits to carry out routine integrity tests, which would be accessed by digging down to man-hole covers and possible non-intrusive checking of the cable in between junction pits with, for instance, ground penetrating radar.


430. Appropriate off-road vehicles would be used to access each jointing pit. Jointing pits would therefore be located adjacent to field boundaries or roads as possible. Kiosks could be used as an alternative maintenance access point to jointing pits.


431. Non-scheduled maintenance to address faults as and when these may arise would also be necessary, and this maintenance could be required in between jointing pit or kiosk locations.


5.6.7 Onshore cable route decommissioning 432. It is anticipated that the onshore cable would be decommissioned (de-energised) and trenched cables left in-situ. However, where cables have been installed in pre- installed ducts (future projects) it may prove possible to extract the cables relatively easily during the decommissioning phase. It has been assumed that the jointing pits and ducts would be left in-situ.


5.6.8 Onshore converter station(s): site description 433. The maximum case for East Anglia THREE is for two adjacent onshore converter stations in the same compound. The minimum case is for one onshore converter station.


434. An onshore converter station(s) is required for East Anglia THREE, and is proposed to be sited adjacent to the north of the existing National Grid Bramford Substation, and directly east of the proposed East Anglia ONE converter station. During the site selection of the East Anglia ONE converter station location, a key factor was to identify a space suitable for converter station sites for two future projects (East Anglia THREE and East Anglia FOUR). “Onshore converter station” means onshore converter(s) housed within one or more converter halls and a compound containing electrical equipment and other associated equipment.


435. The purpose of the converter station(s) is to change the electrical current from HVDC to HVAC, to be compatible with the National Grid in the electrical transmission network.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 97


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114