 Construction Consolidation Sites – nine in total mostly on brownfield sites up to 10ha in total.


 Removal of the haul road and reinstatement of land and features along 37km of the onshore cable route.


344. The onshore cable route is approximately 75m in width except at the HDD locations where it is wider to allow for lay down areas for the HDD kit. Within the onshore cable route a working width of 55m will be required. Within this working width there will be space for haul road, temporary laydown areas, jointing pits and temporary spoil storage.


5.6.4.1 Pre-construction Works 345. Pre-construction activities would include the following:


 Topographic surveys (for engineering purposes);  Ecological pre-construction work (including, for instance, hedgerow removal);  Archaeological pre-construction work;  Drainage surveys;  Geotechnical and ground stability surveys; and  Pre-entry records and requirements.


346. The information from such surveys would form the basis for agreement on final reinstatement of the land after construction.


5.6.4.1.1 Boundaries 347. Temporary fences would be erected along the boundaries of the working width. The type of fencing to be used would be determined through consultation with the landowner or occupier. Gates and stiles would be incorporated as appropriate (for example, where farm access would be maintained).


348. High visibility fencing would be installed to denote infrastructure crossings (such as gas pipelines or overhead power lines).


349. Within the corridor and wherever practicable EATL would minimise the number of trees to be felled and only trees that have been specifically identified would be removed. Similarly, hedgerows would only be removed where absolutely necessary for the construction of the cable route and only where prior agreement has been obtained. A reduced working width of 35m is proposed at hedgerows classified as


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 77


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114