This page contains a Flash digital edition of a book.
 Position HDD rig adjacent to joining pit and drill a pilot hole up to 1,100m from the base of the cliff;


 Enlarge the pilot hole;


 Install the casing pipe or duct in the enlarged hole, and install messenger wire and winch for future cable installation within the duct;


 If required, drawback of the offshore duct end and natural burial by sandy sediments until required to be jointed to the export cable; and


 Demobilise construction equipment and re-instate the site to its previous condition.


287. Once the export cable is ready for jointing to the cables within the cable ducts at the landfall, the following steps would be required:


 On arrival of the export cable installation vessel, the duct exit would require de- burial. This would most likely be achieved using a mass flow excavator.


 The export cable installation vessel would be positioned by anchors prior to undertaking the cable pull in operations, facilitated by a pre-installed messenger wire within the HDD duct and a pre-mobilised pull-in winch located in the onshore transition pit.


 Following completion of the pull in operation (and subsequent termination and cable testing) the export cable installation vessel would commence cable lay operations. If the cable is installed as bundled pairs, then trenching is the most likely means of cable protection in this area, whilst for single cables, ploughing would be the preferable means of burial due to the nature of the sea bed in this area (out-cropping London Clay).


 Subsequent to the cable lay operations, the cable in the transition zone between the HDD duct and full depth of cable trench would be lowered utilising diver based jet lancing and dredging operations, most likely supported from a small anchored or spudded barge.


5.5.2.2 Transition Pits 288. Transition pits would be required at an appropriate distance behind the shore to house the offshore to onshore cable joints. Each transition pit would comprise a buried concrete-lined structure. The purpose of the transition pit at the landfall would be to provide housing for the joint between the heavily armoured marine cables and the onshore cables.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 64


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114