This page contains a Flash digital edition of a book.
suction caisson. If this foundation type is adopted, detailed work would be required pre-construction to determine preparation required for each foundation. Ground preparation requirements in terms of the maximum volume of excavation would be less than that required fromgravity base structures.


5.4.4.3.3 Installation method for suction caisson foundations 96.


Suction caisson foundations are most likely to be towed to site by tugs as they are designed to be buoyant. The caisson skirt and shaft are generally delivered and installed as a single part.


97. The overall basic installation methodology would typically be as follows:


 Confirmation investigation of sea bed to ensure no obstructions are present (this would be on-going throughout the installation process);


 Prepare sea bed (if necessary) prior to installation;  Suction caisson foundation towed to site via barges;  Suction caisson foundation is ballasted and lowered to sea bed;  Initial penetration occurs under foundation self weight;


 Pumps are attached to caisson and water evacuated. Typically there are a number of chambers within the caisson in order to implement a controlled installation and to control levels. Water jetting may be used at the tip of the skirt to facilitate penetration;


 Install scour protection (likely to be rock dumping); and  Spoil removal and disposal for suction caisson foundations.


5.4.4.3.4 Type of scour protection for suction caisson foundations 98.


Scour protection would be provided around the installed suction bucket. The requirements would be similar to those listed for gravity base structures above. The quantities and extent of scour protection would be dependent on current speed, sediment type and the foundation details.


99.


As for gravity base structures, if this foundation type is adopted, detailed pre- construction work would be required to design the scour protection for each foundation.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 22


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114