This page contains a Flash digital edition of a book.
67.


Some gravity base structure solutions may require the injection of a cement grout mix under the foundation to strengthen the sea bed and / or fill voids.


5.4.4.2.2 Sea bed preparation and penetration for gravity base structures 68.


Gravity base structures may require sea bed preparation to level the sea bed, provide a base with adequate bearing capacity and to ensure adequate contact between foundation base and sea bed.


69.


Within the East Anglia THREE site, sand waves of varying magnitude are known to be present. Gravity base structures are not suitable in areas of very large and mobile sand waves but they could be used in areas where smaller sand waves are present. At these locations the sea bed may need to be excavated to the trough of the sand wave and the underside of the base would be placed at this level on a bedding layer.


70. 71.


At some locations, excavation of upper sediments may be required to reach a competent formation level.


Sea bed preparation would consist of dredging works and the installation of a bedding and levelling layer. The dredging works are likely to be carried out using a trailer suction hopper dredger. The bedding and levelling layer installation would be undertaken by a fall pipe vessel.


72.


The dredged sand would be deposited at an agreed disposal area as close as possible to the installation operations. This site will be determined through further consultation, it is anticipated that EATL will seek to designate the East Anglia THREE site as the disposal area for dredged materials. However, for locations requiring significant excavation, it is likely that some of this dredged material would be used later for infill works, and as ballast material.


73.


The preference is that gravity base structure foundations are installed where no or limited ground preparation is required and micro-siting would be used to minimise any dredging requirements. Table 5.6 below shows two scenarios, based on a 7MW and 12MW gravity base structures.


Table 5. 6 Estimated dimensions of excavation for gravity base structures Wind turbine size (MW) 7


Max. overall dredge area (m2)


12


1,257 2,828


Max. volume of excavation (m3)


17,000 26,000


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 17


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114