This page contains a Flash digital edition of a book.
 Uraduct. 5.4.11.16 Inter-array cable protection: cable crossings.


221. It has been anticipated that there will be up to ten inter-array cable crossings within the East Anglia THREE site. Where cable crossings occur they will be protected using the methods as used for cable protection when cable burial is not possible (as described in section 5.4.11.5). The anticipated maximum footprint of cable crossing within the East Anglia THREE site would be 720m2 with the maximum height of 1.5m.


5.4.11.17 Inter-array cables: hook up methods to wind turbines


222. It is planned not to use divers for cable installation. The hook up would be done by the support of ROV vehicles.


223. A typical methodology for installing the cable into a J-tube is as follows. However, alternative cable entry details and installation methods are being considered.


 A cable barge or a specialist cable installation vessel would be mobilised to the site. The cables would be supplied either on cable reels or as a continuous length.


 The vessel transits to site and takes up station adjacent to a wind turbine structure and either holds station on DP or sets out a mooring pattern using anchors. A cable end is floated off from the cable reel on the vessel towards the wind turbine and connected to a pre-installed messenger wire in the J-tube. The messenger wire allows the cable to be pulled up the J-tube.


 The cable is pulled up the J–tube in a controlled manner with careful monitoring. When the cable reaches the cable temporary hang-off (at a later date a cable jointer would terminate the cable and install the permanent hang-off), the pulling operation ceases and the cable joint is made. The cable is laid away from the J-tube on the first wind turbine towards the J-tube on the second wind turbine.


 When the cable installation vessel nears the J-tube on the second wind turbine structure, the cable end is taken from the reel, ready for pulling up the J-tube.


 The cable end is attached to the messenger wire from the bellmouth of the second J-tube. A tow wire is taken from the cable installation vessel and connected to the messenger line at the top of the J–tube and the pulling operation is repeated in the same manner as was employed at the first J-tube.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 50


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114