Installation of up to four cables along 37km of the cable route (mostly via open trenching) with haul road along the entire length together with installation of up to eight ducts for cables from future projects (East Anglia THREE and East Anglia FOUR). Note that the haul road is a maximum of 32.84km as there are gaps for the HDD crossings.
HDD for up to eight ducts at seven points along the route (the eighth HDD is at the landfall as discussed above).
Removal of the haul road and reinstatement of land and features along 37km of the cable route.
329. Therefore for East Anglia THREE the following works are required at a later date:
Creation of up to four jointing pits (assuming each cable jointed in its own pit) at up to 61 locations along the cable route.
Transport to site, cable pulling and jointing at up to 244 jointing pits at up to 61 locations. Note that if ducts are used, shorter lengths of cable will have to be employed in order not to damage cables fromresistance to pulling cable through ducts. Therefore, for this Scenario more joints and hence jointing pits are required than if cables are installed directly into trenches.
Temporary lay-down areas of 300m2 at each of up to 61 locations (assuming that one lay-down area serves both pits).
Access via existing roads and tracks and therefore no haul road is required except for where joints are placed in remote areas. A maximum of 16.1km of 5.5m width haul road is required. Temporary track matting may be required if ground conditions are very poor.
Construction Consolidation Sites – nine in total mostly on brownfield sites up to 10ha in total.
Reinstatement of land.
330. The onshore cable route is approximately 75m in width except at the HDD locations where spacing of ducts will be wider. Except in these HDD locations, within the onshore cable route a working width of 55m will be required. Within this working width there will be space for any haul road, temporary laydown areas, jointing pits and temporary spoil storage.
Preliminary Environmental Information May 2014
East Anglia THREE Offshore Windfarm
Chapter 5 Description of the Development Page 73
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100 |
Page 101 |
Page 102 |
Page 103 |
Page 104 |
Page 105 |
Page 106 |
Page 107 |
Page 108 |
Page 109 |
Page 110 |
Page 111 |
Page 112 |
Page 113 |
Page 114