export cables immediately, or ducts would be left within the sea bed until the cables are installed within them and connected to offshore export cables.


275. The short HDD method of installing the export cables is similar to that for the long HDD method with the exception of a shorter offshore set back distance. Offshore, a trench would be excavated using a barge based excavator or suction dredger from the duct end towards deeper water and softer sediments whereby a plough or jetting tool could be used to install the export cable further offshore.


276. In the short HDD option the HDD exit point would require temporary access from the cliff top to the beach area. It is proposed that any temporary works access would be constructed to the northeast of the proposed HDD site, in order to minimise disturbance to the SSSI at Bawdsey Cliffs and to avoid vegetated shingle at landfall. A site investigation has demonstrated that although the Red Crag is present inland it is absent along this section of the coast. Temporary access would most likely comprise a ramp constructed over the cliff. The temporary access would be required for a tracked excavator, which would be used to prepare the exit point and make the connection with the duct. The excavator and site personnel must have a safe exit from the beach at all times.


277. The beach access will remain in position for the duration of the drilling programme and for the cable landing, but actual access to the beach will only be required for a few hours to excavate and rebury the exit pit each time a duct is pulled into the drill bore, or when the cable is installed into each duct. During duct and cable pulling operations access to the beach may need to be restricted or sections of beach may need to be temporarily closed for the day to protect members of the public from construction hazards. At all other times the beach will remain open and no plant or equipment will be present.


5.5.2.1 Horizontal directional drilling (HDD) 278. The method comprises a three stage process wherein:


 The first stage drills a pilot hole along the designated route;


 The second stage enlarges the hole by passing a larger cutting tool known as the back reamer; and


 The third stage places the product, casing pipe or duct in the enlarged hole.


279. HDD is undertaken with the help of a viscous fluid known as drilling fluid. It is a usually mixture of water and bentonite or polymer continuously pumped to the


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 61


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114