This page contains a Flash digital edition of a book.
 Excavation as appropriate;  Installation of blinding (concrete);  Construction and installation of timber formwork and supports;  Installation of steel cages for structural support (rebar);  Placement of structural concrete around rebar; and  Curing of concrete and finishing.


457. It should be noted that prior to undertaking detailed ground investigations, it is not yet possible to determine whether piling is required in order to support the foundations and limit settlement to acceptable levels.


5.6.10.8 Construction: Buildings 458. The proposed building substructures are typically predominantly composed of steel and cladding materials. The structural steelwork would be fabricated and prepared off site and delivered to site for erection activities. The steelwork would be erected with the use of cranes.


459. Cladding panels (typically composite) would also be delivered to site ready to erect and be fixed to the steelwork. A variety of means would be used to install the cladding, depending on the particular area being accessed. The control building would include the construction of brick or blockwork partitions and would include a number of follow on trades for plumbing, plastering, and low voltage mechanical and electrical installations.


5.6.10.9 Construction: Installation Works 460. For the installation and commissioning phases of the project a variety of specialist activities would be required. The main aspect of installation within the building would be the valves themselves. These are typically installed with the use of specifically designed beams that are part of the structural fabric of the building.


461. Another main part of the installation would be the transformers. These items of plant would be delivered sealed and would be particularly bulky, heavy items. Due to their size and weight they would be delivered via specialist means and offloaded with the use of a mobile gantry crane.


462. The majority of the remaining HVDC equipment, HVAC equipment and cooling towers would be erected with the use of small mobile plant and lifting apparatus.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 5 Description of the Development Page 103


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114