If bats or signs of bats were found in any of the features, a European Protected Species (EPS) licence for bat development would be necessary to work on or remove the trees.


119 120


If roosts are identified, and destruction cannot be avoided, further surveys may be necessary to inform the EPS licensing process.


The Bat Conservation Trust (BCT) Guidelines (BCT, 2007) recommend that when a tree with high potential to support roosting bats is felled, a bat box be erected on a nearby tree. It should be assumed that a tree with high potential to support roosting bats may be used by bats at some point even if no bats have been recorded using it during the surveys. Therefore before any trees which are classified as Category 1, 2 or 3 in terms of their bat roost potential are felled, a Schwegler 1FF bat box is erected on a nearby tree. This would help to compensate for the potential roost lost and help to ensure the potential roost „stock‟ of an area is not decreased as a result of the works. Schwegler 1FF bat boxes are known to be used by a variety of bat species and are also unlikely to be used by nesting birds which can out-compete bats for bat boxes during the nesting bird season.


121


It is acknowledged that Little Blakenham Pit SSSI which is a known hibernation site for bats is situated approximately 1km to the north west of the Onshore Cable Route and approximately 3km for the Converter Station. There is therefore the potential for lighting impacts on favoured commuting corridors in the proximity to the Onshore Cable Corridor and Converter Station.


122


There would be no 24 hour lighting along the Onshore Cable Route except at HDD locations and all Construction Consolidation Sites. There would however need to be 24 hour lighting at the Converter Station only for key construction activities.


123


Pre-construction activity surveys would be undertaken to identify key commuting routes around the Converter Station. These would follow the same methodology as the baseline surveys undertaken for the ES. This information would then form the basis of a lighting strategy focused on minimising impacts during sensitive construction months. This strategy would be agreed with the local authorities and construction implemented in line with the strategy.


124


The pre construction activity surveys and the pre-construction walkover survey outlined in Section 3.2.1.2 would also be used to inform micro-routing decisions for during-construction mitigation


Outline Landscape and Ecological Management Strategy. Version 2


Page 37


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129