1 Ecological Mitigation Plan for SPA Non-breeding Birds and Schedule 1 Breeding Birds


1.1 Introduction 1.


This Ecological Mitigation Plan (EcMP) for SPA and Schedule 1 Birds forms part of the overall Outline Landscape and Ecological Management Plan (LEcMP) for the onshore cable route of the East Anglia ONE offshore wind farm. The production of such a plan is requirement of the [draft] Development Consent Order (DCO). The LEcMP sits within the Code of Construction Practice (CoCP), itself a requirement of the [draft] DCO.


2. This part of the LEcMP is targeted at birds that are the Deben Estuary Special Protection Area (SPA) interest features and birds that are listed on Schedule 1 of the Wildlife and Countryside Act 1981 (WCA). These two groups of birds are addressed together in this part of the LEcMP to ensure that the mitigation actions targeted at one particular bird species do not conflict with the requirements of another.


3. This plan is supported by the following Appendices Appendix 1:


Appendix 2: Appendix 3: Appendix 4: Appendix 5: Brent Goose distribution in the winter of 2011-12 Avocet distribution in the winter of 2011-12 Area of Potential Nesting Marsh Harrier Habitats


Cetti's Warbler Activity and Horizontal Directional Drilling (HDD) Location: Martlesham Creek


Cetti's Warbler Activity and Horizontal Directional Drilling (HDD) Location: Wetland on Mill River south of Hemley


1.2 Objective of the EcMP for SPA and Schedule 1 Birds


4. The objectives of this EcMP is to ensure that measures are taken to avoid or minimise impacts on those birds that are interest features of the Deben Estuary SPA and Schedule 1 Birds during the construction phase of the onshore electrical transmission works of East Anglia ONE. It details mitigation measures to reduce the impact on Deben Estuary SPA birds, in particular dark bellied brent geese, that ensures no effect on the integrity of the site should an Appropriate Assessment have been required as part of the Habitat Regulations Assessment process.


EcMP: Deben Estuary SPA & Schedule 1 Birds


Page 1


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129