This page contains a Flash digital edition of a book.
22.7.3 Potential Cumulative Impacts during Decommissioning


22.7.3.1 Landfall and onshore cable route 211. It is anticipated that the onshore cable would be decommissioned (de-energised) and most likely the cables left in-situ. However, where cables have been installed in pre-installed ducts (future projects) it may prove possible to extract the cables relatively easily during the decommissioning phase. It has also been assumed that the jointing pits will be left in-situ.


212. Should East Anglia THREE and FOUR be installed using pre-installed ducts, extraction of the cables during the decommissioning phase would be anticipated to have a similar impact as for East Anglia ONE. This assumes that the jointing pits and cable ducts will be left in-situ.


213. The worst case scenario will be if excavation of the buried cables is required for decommissioning and if this is undertaken sequentially for each of East Anglia ONE, East Anglia THREE and East Anglia FOUR. Impacts would be similar to but of lower magnitude for construction under Scenario 2 as discussed in section 21.6.1.


22.7.3.2 Converter station 214. The details regarding the decommissioning of the converter stations are currently unknown. The worst case scenario is considered to be consecutive removal and reinstatement. Decommissioning would be undertaken in line with legislation, policy and best-practice guidance in place at the time.


22.8 Inter-relationships


215. Parameters or “sources” that are considered to interact with receptors identified in this chapter are listed in Table22.15 below.


Table 22.15. Inter-relationships with Land Use Inter-relationship


All Phases Soils, Geology and Ground Conditions


Ecology (Invasive species and Nature Conservation Sites)


Onshore archaeology and cultural heritage


Traffic and Transport (Roads and Access)


Socioeconomics Section where addressed 22.5, 22.6, 22.7 22.5, 22.6, 22.7 22.5, 22.6, 22.5, 22.6, 22.7 22.5, 22.6, 22.7 Linked Chapter Chapter 19 Chapter 23 Chapter 25 Chapter 27 Chapter 28


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 22 Land Use Page 59


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75