This page contains a Flash digital edition of a book.
22.6.1.4.2Converter station 125. Soil will be excavated for the foundations of the converter station. It is anticipated that all excavated material will be used in the creation of bunds around the converter station and there will be no offsite disposal. The magnitude of the impact is therefore considered to be medium. The soils identified at the indication converter station location are considered to be of low environmental value and thus of low sensitivity. Therefore the impact significance is predicted to be minor adverse.


22.6.1.5 Impact 5: Potential spread of disease 126. This section considers the potential spread of disease that could be caused by construction works. For potential impacts of construction to invasive non-native species, please see Chapter 23 Ecology.


22.6.1.5.1 Landfall and onshore cable route 127. The nearest incidence of a notified scheduled disease (for potato cyst nematode) to the landfall was more than 5km west of the landfall. There are three incidences of potato cyst nematode along the onshore cable route. These are located at Kirton Lodge and Kembroke Hall (between Kirton and Newbourne) and at Sycamore Farm (south of Little Blakenham) (Figure 22.5).


128. The sensitivity of the potato cyst nematode to the potential impacts of construction is considered to be high since this source of contamination is recognised as such at a national level (Table 22.7), however the instances of these sources of contamination are few, as one location is located approximately 300m away from the onshore cable route, while two other locations cross the route. Embedded mitigation includes adhering to good practice construction and agricultural practices, thus minimising the transfer of any plant and animal diseases. These are outlined in Table 22.3. Additional mitigation is suggested in Table 22.13 below.


129. A pre-construction survey would be undertaken to obtain up-to-date information on the status of non-native invasive species within the landfall and onshore cable route; this can be combined with other pre-construction ecological surveys (see Chapter 23 Ecology).


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 22 Land Use Page 41


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75