This page contains a Flash digital edition of a book.
22.6.2.4 Impact 4: Impacts to soils


22.6.2.4.1 Landfall, onshore cable route and converter station 161. It may be necessary to excavate soil to access the cable for maintenance activities. It is anticipated that these events would be highly localised and of short duration. Soil handling would be undertaken as described in the embedded mitigation section 22.3.3. It is likely that soils would be re-used on site appropriately. Soils that cannot be reused will follow a waste hierarchy. Following implementation of measures committed to within embedded mitigation, the magnitude of this impact is therefore considered to be low and the sensitivity of local soils is considered to be low. Therefore the impact significance is considered to be negligible.


162. Routine maintenance works would be required during the operational phase; however, this access would be via jointing pits or kiosks. Maintenance may include the excavation of soil in order to access the cables. It is anticipated that these events would be highly localised, temporary and of short duration. Jointing pits will be located be located away from watercourses and adjacent to field boundaries (avoiding rootzone) or roads and appropriate off-road vehicles would be used to access each of these. Overall a negligible impact is predicted.


22.6.2.5 Impact 5: Biological contamination


22.6.2.5.1 Landfall, onshore cable route and converter station. 163. Vehicle movements would only be needed in the event of requirement to maintain cables and this would be a much lower level of movements than during construction. Mitigation measures would ensure there is no impact from biological contamination during operation.


22.6.2.6 Impact 6: Impacts to Public Rights of Way and Cycle Routes


22.6.2.6.1 Landfall and onshore cable route 164. As all diversions would be removed and PRoW reinstated post-construction no impact is predicted during operation.


22.6.2.6.2Converter Station 165. PRoWmay be subject to visual impacts during operation, these are discussed within Chapter 29 Seascape, Landscape and Visual Amenity. During operation, access along the bridleway (crossing 44) would be open and no diversion would be required, therefore no impact is predicted.


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 22 Land Use Page 47


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75