This page contains a Flash digital edition of a book.
14.


 Reinstatement of land. The onshore cable route is approximately 75m in width except at the HDD locations


where spacing of ducts will be wider. Within the onshore cable route a working width of 55m will be required. Within this working width there will be space for any haul road, temporary laydown areas, jointing pits and temporary spoil storage.


15. Note that the haul road requirement under this scenario is currently being reviewed. In the original design iteration for this option it was assumed that all access to the onshore cable route would be made via those access points identified for East Anglia ONE. This would in places require the removal of hedgerow and reinstatement of haul road to access isolated locations for jointing pits (i.e. those locations which are far removed from field boundaries adjoining roads).


16. It is desirable to reduce the requirement for haul road for two reasons. Firstly under


Scenario 1 the bulk of the materials delivered to and taken off site will be for the creation of the haul road itself. Any reduction in haul road requirement would reduce overall material volumes and therefore vehicle movements. Secondly, if existing tracks could be upgraded to access remote jointing pit locations this would reduce disruption to arable fields (and hedgerows and other sensitive habitats) and provide an upgrade to the local infrastructure.


17. Use of existing tracks would be subject to consultation with landowners, therefore


the red line boundary displayed on the figures for this PEIR show these areas within the boundary in order to prompt consultation on the possible use of new access routes not previously consulted on for East Anglia ONE.


18. 19. 20. For Scenario 2 it is assumed that the whole of the onshore cable route would consist


of open cut trenches, except at the HDD locations shown in Figure 21.4. Full details of the two scenarios being considered is provided within Chapter 5


Description of the Development. For each impact, the assessment utilises a worst case approach for each of the two


scenarios described above. The design parameters that constitute worst case vary depending on the potential impact under consideration and are used as detailed in Table 22.2 below.


21. Only those design parameters with the potential to influence the level of impact are identified. Therefore, if the design parameter is not described below, it is not considered to have a material bearing on the outcome of the land use impact assessment. For example: the number of vehicles required during construction


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 22 Land Use Page 7


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75