86. Magnetic fields are produced by the current within a conductor. The current varies according to the electrical power requirement. The higher the current the stronger the magnetic field that is produced. Microteslas (μT) are the unit of measurement used for magnetic fields. In the UK, the Earth has a natural magnetic field of approximately 50μT.
87. In contrast with electric fields, magnetic fields are not readily screened by trees and
ordinary building materials. However, they diminish rapidly with distance from the source. The proposed East Anglia THREE project comprises underground HVDC cables from the landfall near Bawdsey to the converter station at Bramford. At the converter station, HVDC would be converted to three-phase AC for connection to the National Grid Electricity Transmission System (NGETS).
88. The converter station would be connected to the existing National Grid substation at
Bramford by means of up to two buried AC cables. These may be installed directly underground or within ducts.
22.6 Potential Impacts Reference should be made to Chapter 5 Description of the Development, for full
89.
details of the activities proposed during the construction phase. However, in summary, the activities considered likely to impact on land use and agriculture are as follows:
90.
Scenario 1 – ducts for the proposed East Anglia THREE and East Anglia FOUR projects would be pre-installed during construction of the East Anglia ONE project
Construction of onshore cable systems including landfall joint transition bay and 48 cable jointing locations – installation techniques include pulling cables through existing ducts;
Construction of an onshore converter station, associated infrastructure and landscaping;
Creation of temporary construction compounds / HDD compound;
Temporary upgrade of existing access tracks, construction of new access tracks and haul roads;
Stockpiling of topsoil and subsoil; Re-use of excavated soil in jointing pits; Disposal of excess spoil offsite to a suitably licenced facility; and Removal and reinstatement of existing drainage systems.
Preliminary Environmental Information May 2014
East Anglia THREE Offshore Windfarm
Chapter 22 Land Use Page 34
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75