This page contains a Flash digital edition of a book.
the route would be revisited for the construction of the subsequent projects for the same time periods. Although the land would be taken out of use up to three times, given the smaller area used for cable installation on subsequent projects, it is considered that this cumulative impact would be no greater than minor adverse significance.


22.7.1.2 Cumulative Impact 2: Environmental Stewardship Schemes 191. For construction of the first project construction would take place for up to 10 weeks at landfall, up to 44 weeks along the onshore cable route and up to 55 weeks at the converter station location. All land would be reinstated with exception of the permanent structures at the converter station compound. Following this, sections of the route would be revisited for the construction of the subsequent projects for the same time periods. Although the land would be taken out of use up to three times, given the smaller area used for cable installation on subsequent projects it is considered that this cumulative impact would be no greater thanminor adverse significance.


22.7.1.3 Cumulative Impact 3: Land drainage 192. For construction of the first project all water crossings would be in place and ducted prior to construction of subsequent projects. There would be a minor adverse impact from the first project (see section 22.6.1.3). There would be limited cumulative impact fromsubsequent projects as disturbance to drainage infrastructure would be limited and there would be little spoil from jointing pit excavation, overall this impact would be negligible. The cumulative impact of undertaking trenching once and up to two further cable pulling operations is not considered to increase above minor adverse.


22.7.1.4 Cumulative Impact 4: Impacts to soils 193. The construction of the first project would lead tominor adverse impacts (see section 22.6.1.4). Impacts from cable-pulling into pre-installed ducts for subsequent projects would be negligible (in line with the assessment of Scenario 1) therefore the cumulative impact of all three projects is considered to remain minor adverse.


22.7.1.5 Cumulative Impact 5: Biological contamination 194. Due to distance from possible contamination sources, no impact is predicted at landfall or converter station (see section 22.6.1.5).


195. Given the distance to the nearest reported source of contamination and assuming adherence to embedded mitigation, the cumulative impact for the onshore cable route would be negligible (see section 22.6.1.5).


Preliminary Environmental Information May 2014


East Anglia THREE Offshore Windfarm


Chapter 22 Land Use Page 56


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75