This page contains a Flash digital edition of a book.
Carbon and energy reduction


Trust following competitive tenders. As well as providing the required technical expertise, the company guaranteed minimum savings for the duration of the 15-year contract. CHP systems are at the heart of NDHT’s strategy, and Kevin Ward believes the potential for CHP systems is ‘huge’, as the energy savings benefits ‘can and do make a dramatic difference for Trusts moving away from steam’.


Solar panels and new lighting At the North Devon District Hospital (NDDH) in Barnstaple an 800 kW CHP system is currently being installed, along with 250 kW solar panels on the roof. A lighting replacement programme is also underway, and so far some 2,000 LED light fittings have successfully been installed, and a further 1,000 LEDs are now being fitted. At the process’s outset, the Trust had some concerns over logistics, and the impact upon patients, but work has gone very smoothly, with minimum disruption. At the three other sites biomass boilers, solar panels, and replacement lighting programmes, are also underway. With no gas supply, Holsworthy Community Hospital is solely reliant on electricity and oil. The new biomass boiler will mark a significant step change, and offer a more resilient solution. The Trust


About Cynergin


Founded in 2000, Cynergin is ‘one of the UK’s leading consultants and energy services companies’. It specialises in delivering ‘performance-based contracts that offer guaranteed reductions in energy consumption, and carbon emissions, and improved operational performance, on the estates of large public sector organisations’.


also ensured that the pellets for the boiler could be locally sourced.


Holsworthy Community Hospital is also installing 35 kW of solar panels, and renewing its oil fired boiler, to give it an emergency back-up. A similar project is underway at South Molton, where, in addition to a biomass boiler, the hospital is installing 50 kW of solar panels and replacing lighting. The NDDH Trust has already started to see the benefits. Since January, across the four sites, the lighting replacement programme has saved £46,000, and 174 tonnes of carbon, and the solar panels, £15,000. The biggest savings are, however, yet to come. When the CHP system at the NDDH site – currently two-thirds of the way through the installation process – is commissioned, Kevin Ward expects the hospital to realise annual savings of £300,000 to £400,000.


Enhanced reliability


He added: “Not only do we have a more reliable and efficient addition to the infrastructure for each site, but when all the technologies have been installed we will have more resilient systems thanks to Cynergin, and expect to be saving £600,000 to £700,000 annually on our energy costs.” Logistically, the lighting programme has been the most challenging, but Kevin Ward is complimentary about the collaborative working practices, and Cynergin’s project management, as well as the work of the Trust’s own Capital and Facilities Team.


Meanwhile, of the importance of internal communication to the replacement programme, with the Trust communicating to staff the reasons for the lighting replacement, its benefits, and how it would put the hospital ‘on a more solid footing’ for the next 10-15 years, he said: “It was important that everyone bought into the lighting project and understood the benefits. The nursing staff helped with


An old steam duct at the George Eliot Hospital, which is replacing its existing plant room, and investing in a LTHW system with new gas-fired boilers and a CHP system.


access, particularly in ‘live’ areas, and patients were moved only when necessary, so as to minimise disruption.”


Data capture


The project partners worked with Salix Finance to secure funding for the energy- saving projects, and found Salix’s compliance tool useful in capturing data and information on the savings that could be generated, the associated technologies, and the paybacks. The estimated savings were calculated by Cynergin, with an assessment of the project business case and savings calculation methodology undertaken by Salix Finance. Finance of £2.8million was sourced from Salix Finance, with the Trust funding the balance; the total capital outlay for the EPC projects was £4.6 m. The projects at NDHT are all on schedule. Kevin Ward says he attributes this to the Trust’s strong relationship with Cynergin, which supplies regular reports and holds weekly meetings. NDHT is considering further projects for the future, and says it and hopes to continue working with Cynergin.


The existing steam boilers at the George Eliot Hospital in Nuneaton. 58 Health Estate Journal September 2016


Yeovil Hospital Yeovil District Hospital in Somerset is an excellent example of what hospitals can do proactively to optimise their energy management. Keen to significantly cut its energy bills and reduce the hospital’s carbon footprint, by ‘spending to save’, Yeovil District Hospital NHS Foundation Trust entered into a 15-year EPC contract with Cynergin to introduce new technologies. These both ensured that it could meet its operational and environmental obligations, and delivered more robust systems. Like many hospitals, Yeovil District


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120