This page contains a Flash digital edition of a book.
Business profile


regarding the steelwork for the trestling and bridge deck. The SPMT’s were offloaded two miles


from the site and the narrow country lanes were temporarily closed while they were manoeuvred to site. All other equipment was transported to site in compact loads due to road restrictions. The steelwork for the trestles, and bridge deck supporting steelwork was carefully selected as it was compact and light enough to construct on site using only a small telehandler.


Once the equipment was constructed and the bridge sections positioned, the completed deck was jacked up to a height of over 3.5metres. ALE was then able to navigate the 6 axle SPMT through the support trestles that the 70te bridge was resting on and loaded it onto the high level support structure. The bridge deck was then transported to the install location and manoeuvred between the narrow installation points. The SPMT’s integrated hydraulic jacking system lowered the bridge into its final position and the SPMT was moved clear of the bridge. Matt Winship Project Engineer at ALE


said: ‘With the location of site being so difficult to access and the inability to use cranes it was clear that the project could present some major challenges. However through careful planning, effective engineering and collaborative working with the client, the installation was a complete success; the bridge deck was installed safely, accurately and to plan.’


Heavy lifting for the Olympics Heavylift’s 1,200te capacity Gottwald AK912-1 heavylift machinery was integral to a high-profile project as part of the preparation for the 2012 London Olympics. ALE completed the installation of the


foot bridge that was used by visitors to access the Olympic facility. The installation required the Gottwald AK912 -1 to be fitted with 71m Maxi Boom, 300te Maxilift Ballast to lift the 196te foot bridge into position creating access to the Olympic site from the Stafford coach/car park. The work was carried out during two night possessions to ensure minimal impact on traffic flow. Andrew Hunt sales manager at ALE said


‘The AK912-1 is an important asset to ALE. Being able to relocate the crane fully rigged using SPMT’s minimised the disruption on site and enabled the project to be completed quicker than alternative cranes could achieve as it would normally take six days to de-rig, relocate and re-rig the crane. ‘While the AK912-1 is permanently


based in the UK, it is only part of our global crane fleet including the AL.SK fleet – the world’s largest capacity land-based cranes – available to be deployed to the UK when


required.’ • Tel: 01889 272 500 www.ale-heavylift.com


September 2013 Page 103


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164  |  Page 165  |  Page 166  |  Page 167  |  Page 168  |  Page 169  |  Page 170  |  Page 171  |  Page 172  |  Page 173  |  Page 174  |  Page 175  |  Page 176  |  Page 177  |  Page 178  |  Page 179  |  Page 180  |  Page 181  |  Page 182  |  Page 183  |  Page 184  |  Page 185  |  Page 186  |  Page 187  |  Page 188