This page contains a Flash digital edition of a book.
Opinion


This July, one of the longest possessions of a British station will begin as a £100 million re-signalling scheme gets under way in Nottingham


I


t’s one of two blockades this summer that are longer than the average Bank Holiday possession. For six weeks trains will be replaced


by buses to the west of Nottingham, as the station layout is completely rebuilt, a new platform created, new signals commissioned, and control transferred to our East Midlands Control Centre in Derby. The area to the east of Nottingham will be served by trains during much of the work, but there will be a period where even they have to stop to allow for the unravelling of 40 years of accumulated operational problems. The last time Nottingham’s station area


was redesigned, the Beatles had just split up, relay-based interlocking was the latest technology and green diesels could still be seen running about the network. Now largely a location where short- formed trains terminate, the through design of the station - with Up and Down lines to the west, a platform (6) that can only dispatch in one direction - has brought with it increasing inefficiencies. Meanwhile, the life-expired signalling equipment is showing its age and the low speeds over Mansfield Junction are also having an effect.


Train tickets discounted for bus journeys To renew the equipment, re-lay more than a mile of track, not to mention all the junctions at the station and Mansfield Junction too, the re-signalling project required more than a series of weekend blockades. Through close working with operator East Midlands Trains, and other users of Nottingham station, including Cross Country, Northern and the freight operators, a solution was found – involving one of the largest replacement bus operations ever set up. This operation will have its own controllers and timetable, bus dispatchers, and joint working with highways to make sure buses don’t get caught in jams. It will also be the first time train tickets will be discounted if you have to take a bus, something which required DfT permission to achieve. This way of working, with longer


closures preferred to weekend blockades, has its attractions for operators, and a nine- day closure of the West Coast main line north of Wigan has also been scheduled for July.


This project will see four junctions redesigned, and three miles of track replaced. It’s part of a rolling programme to


replace nine WCML junctions that currently require bank holiday closures whenever they need tamping – currently once a year.


By moving the sets of points further apart, so they don’t sit ‘toe-to-toe’, each line can be tamped in a normal overnight eight-hour possession. While there will still be the need for weekend possessions of the line in future, this will make a huge difference to the amount of disruption caused. Network Rail will also be increasing line speeds over the junctions so they more closely match, as far as possible, the speed over the diverging route.


A clearer message to customers This work could have been achieved by arranging a series of bank holiday and weekend blockades, stretching into next year. However, closing the route for multiple bank holidays would require a


different system of buses and re-routed trains for each event, plus a public communications push from the operators. With a longer, more concentrated blockade, operators can simplify their message to customers and make clear the alternative arrangements. Network Rail has also been involved in the communications push around the blockade, with roadshows and advertising campaigns to match. With the massive modernisation of


the network being undertaken in the next five years, one of the challenges we face is finding innovative ways of keeping people moving while we do it, and communicating the changes as they come.


Artist’s impressions of the proposed southern side concourse, above and below


July/August 2013 Page 21


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148